S.V.V.Rambabu vs. The State Of Andhra Pradesh
Held
The Court disposed of the Writ Petition by issuing a direction to the respondents to take necessary steps for the payment of the remaining 21 unpaid bills as expeditiously as possible, and at any rate, within a period of two months from the date of receipt of the order. The Court acknowledged the petitioner's claim for interest but advised the petitioner to raise this claim before the appropriate forum if they were so advised. The Court did not make any specific finding on the illegality or arbitrariness of the respondents' action beyond directing prompt payment. The issue of GST and interest was implicitly addressed by directing payment of the bills, with the interest component to be pursued separately. No specific provisions of the GST Act were discussed or interpreted, as the dispute primarily concerned the payment of contractual dues.
Facts
The petitioner, S.V.V. Rambabu, filed a writ petition seeking a Mandamus to direct the respondents, including the State of Andhra Pradesh and its Irrigation Department officials, to pay bills for 27 works executed under various agreements. The total value of these works was Rs. 2,18,92,453/-, with an agreed GST of 12%. The petitioner also claimed interest from the date of completion of the works. The petitioner contended that the respondents' inaction in paying the bills was illegal, arbitrary, and violative of natural justice and constitutional provisions. The respondents, through the Learned Government Pleader for Irrigation, submitted written instructions stating that 6 out of the 27 bills had been cleared, and payment for the remaining bills would take time. They requested four months to process the payments.
Key Issues
1. Whether the respondents' failure to pay the bills for the executed works, totaling Rs. 2,18,92,453/- with 12% GST, is illegal, arbitrary, and violative of the principles of natural justice and Articles 14, 19(1)(g), and 21 of the Constitution of India? Petitioner's Arguments: The petitioner argued that the respondents' inaction in paying the bills for the 27 works was illegal and arbitrary. They contended that this delay violated fundamental rights guaranteed under the Constitution, including the right to carry on business (Article 19(1)(g)) and the right to life and personal liberty (Article 21), which encompasses the right to livelihood. The petitioner also asserted that the delay breached the principles of natural justice by not fulfilling contractual obligations promptly. Respondents' Arguments: The respondents did not contest the validity of the bills or the works executed. Their primary submission was that out of the 27 bills, 6 had already been cleared. For the remaining 21 bills, they stated that processing payments would take time and requested a period of four months to complete the necessary actions for payment.
AI-generated summary — verify with the full judgment below
Cause title — parties, addresses and appearances
ORDER:
The present Writ Petition is filed under Article 226 of the Constitution of India to issue a Writ of Mandamus or any appropriate writ declaring the action of the respondents in not paying the bills for execution of 27 works vide (i) Agreement No.69/2021-22, Dt:31-07-2021 (ii) Agreement No.08/2022-23, Dt.23-04-2022 (iii) Agreement No.09/2022-23, Dt.23-04-2022 (iv) Agreement No.10/2022-23, Dt.23-04-2022 (v) Agreement No.06/2022-23, Dt.23-04-2022 (vi) Agreement No.05/2022-23, Dt.23-04-2022 (vii) Agreement No.07/2022-23, Dt.
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Andhra Pradesh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.