M/S. Vasista Engineerings vs. The State Of Andhra Pradesh
Held
The Court held that the respondents' action in not releasing the final bill amount to the petitioner was unjust and untenable, given the undisputed position regarding the execution of the work. The Court acknowledged the petitioner's claim and the respondents' admission of the work's completion. While the respondents cited the absence of an LOC and budget as reasons for non-payment, the Court found these reasons insufficient to justify the delay in releasing the due and payable amount. The Court directed the respondents to arrange for the payment of the amount due to the petitioner, after effecting statutory deductions, as expeditiously as possible, and at any rate, within a period of six weeks from the date of receipt of the order. The Court explicitly noted that the issue of GST reimbursement was mentioned in the counter-affidavit but did not form the primary basis for the Court's direction on the payment of the principal amount.
Facts
The petitioner, M/s. Vasista Engineerings, filed a writ petition seeking a direction to the respondents to release a final bill amount of Rs.17,03,753/- for irrigation works executed under two agreements. The petitioner stated that the works were completed, inspected, quality checked, and the final bill was approved. However, payment was not made despite repeated requests, causing financial hardship. The respondents, through a counter-affidavit filed by the 5th respondent, did not dispute the work executed. They indicated that payment was delayed due to the absence of a Letter of Credit (LOC) and sufficient budget. The counter-affidavit mentioned that GST amounts would be reimbursed to the agency in the final bills after the release of the LOC.
Key Issues
1. Whether the respondents' action in withholding the payment of the final bill amount of Rs.17,03,753/- for the irrigation works executed by the petitioner is unjust and untenable, considering the undisputed completion of the work. Petitioner's Argument: The petitioner argued that they had completed the irrigation works as per the agreements, and the final bills were approved. Despite repeated requests, the respondents failed to release the payment, causing severe financial distress. They sought a direction for the release of the undisputed amount. Respondents' Argument: The respondents, in their counter-affidavit, did not dispute the execution of the work. However, they stated that payment was not made due to the lack of a Letter of Credit (LOC) and sufficient budget. They also mentioned that the GST amount would be reimbursed after the release of the LOC.
Sections Cited
None explicitly mentioned in the judgment text provided, other than general reference to GST amounts.
AI-generated summary — verify with the full judgment below
Cause title — parties, addresses and appearances
ORDER:
The present Writ Petition is filed seeking a direction to the respondents to release the final bill amount of Rs.17,03,753/- for execution of irrigation works under Irrigation Department, under (1) Agreement No.67/2020–21, dated 01.7.2020, Quality Control Certificate No.2233, and (2) Supplementary Agreement No.115/2020–21, dated 01.10.2019. 2. Learned Counsel for the petitioner states that the petitioner completed the above mentioned works and the concerned officers inspected the same, conducted quality check also and thereafter relevant entries were made in the Measurement Book. Further that the
2
respondents
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Andhra Pradesh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.