Ketha Venkata Ramana Reddy vs. The State Of Andhra Pradesh
Held
The Court held that the respondents' action in not releasing payments for the executed works was unjust and not tenable, given the undisputed execution of the works by the petitioner. The Court found the non-payment to be unreasonable. The ratio decidendi is that government authorities cannot arbitrarily withhold payments for completed works without valid justification, and such inaction is unsustainable. The Court directed the respondents to arrange for the payment of the amounts due and payable to the petitioner, after effecting statutory deductions, as expeditiously as possible, within a period of three months from the date of receipt of the order. The Court explicitly left undecided the petitioner's claim for interest, advising the petitioner to raise such a claim before the appropriate forum if advised.
Facts
The petitioner, Ketha Venkata Ramana Reddy, filed a writ petition challenging the respondents' inaction in paying bills for various works executed under six different agreements. The total outstanding amount claimed by the petitioner is Rs. 69,26,623/-. The petitioner contended that the works were completed, measurements recorded, and bills lawfully due were not released, causing prejudice. The respondents, represented by the State of Andhra Pradesh, submitted written instructions indicating that BRO proposals were sent for Head Office approval and payment would be cleared upon government release of BRO funds. The Court noted the undisputed execution of works and non-payment.
Key Issues
1. Whether the respondents' action in not paying the bills for the executed works, totaling Rs. 69,26,623/-, is illegal, arbitrary, and unjust, warranting a direction for payment under the relevant contractual and statutory provisions governing payments for government works? Petitioner's arguments: The petitioner argued that the works were executed in all respects, measurements were recorded, and despite entitlement, the bills were not released, causing serious prejudice and irreparable loss. The petitioner sought a consequential direction for payment. Respondents' arguments: The respondents, through written instructions, indicated that BRO proposals were submitted for approval and payment would be cleared once the government releases the BRO. They did not dispute the execution of works or the non-payment but cited procedural delays and dependency on government fund release.
AI-generated summary — verify with the full judgment below
Cause title — parties, addresses and appearances
ORDER:
Heard learned counsel for the petitioner. Also heard learned Government Pleader for Irrigation & CAD and the Learned Government Pleader for Finance & Planning appearing for the respective respondents. With the consent of both sides, the Writ Petition is disposed of, at the stage of admission.
The present Writ Petition is filed to declare the action of the respondents in not paying the bills for execution of various works by petitioner under 1) Agreement No.32/2021-22, dated 31.12.2021, to an amount of Rs.9,71,686/-, 2)Agreement No.33/2021-22, dated 31.12.2021 to an amount of Rs.16,68,747/-, 3)Agreement No.
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Andhra Pradesh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.