Vijay Electrical Engineering vs. The State Of Ap

WP/33999/2022HC Andhra PradeshGSTCNR APHC01055654202209 October 2023Bench: RAVI CHEEMALAPATI37 pages
AI SummaryDismissed

Held

The Court held that the petitioner's tender was rightly rejected because they failed to meet the essential and mandatory eligibility criteria stipulated in Clause 7 of the tender specification. Specifically, the petitioner's wireman permit for R. Bala Krishna had expired on July 14, 2021, and was not revalidated. The Court found that Clause 3 of the tender specification, titled 'FILLING OF SCHEDULE,' did not contain any mandate that registered contractors alone were eligible to submit tender forms; it only stated that work contracts would be awarded to registered contractors. Therefore, being a registered contractor was not an essential eligibility criterion for submitting a tender. Regarding the 5th respondent's experience certificate, the Court held that since the tender specification did not explicitly require supporting documents like EPF, ESI, and salary certificates, their non-production would not invalidate the experience certificate. Consequently, the Court found no valid or reasonable grounds to interfere with the respondents' action, deeming it not arbitrary, irrational, mala fide, or contrary to law. The writ petition was dismissed, and the interim orders were vacated.

Facts

The petitioner, Vijay Electrical Engineering, challenged an LS Agreement dated October 1, 2022, awarded by the Superintending Engineer, Operation Circle, APCPDCL (4th respondent) to the 5th respondent. This agreement was for the operation and maintenance of seven 33/11 KV Sub Stations for the period September 1, 2022, to August 31, 2024. The petitioner contended that the award was illegal, arbitrary, and contrary to tender conditions, arguing they were a more qualified and eligible tenderer. The petitioner had obtained an Electrical Contract License Grade-A, renewed until July 14, 2023, and was registered with the 2nd respondent. The 5th respondent was awarded the work. The petitioner sought to set aside the agreement and have the work awarded to them. Subsequent applications were filed by the 5th respondent to vacate the interim order granted to the petitioner, and by APCPDCL (respondents 1-3) to vacate the same interim order.

Key Issues

1. Whether the tender of the petitioner was rightly rejected for non-fulfillment of essential and mandatory conditions as per Clause 7 of the tender specification, specifically regarding the eligibility for manpower supply on outsourcing, which requires supervision and wireman permit holders. (Question of law and fact) 2. Whether the petitioner's contention that Clause 3 of the tender specification mandates that only registered contractors are eligible to submit tender forms is correct, and if Clause 3 specifies eligibility criteria. (Question of law) 3. Whether the 5th respondent's experience certificate, submitted without supporting documents like EPF, ESI, and salary certificates, should invalidate their bid, given the tender specification did not stipulate such requirements. (Question of law and fact) Petitioner's arguments: The petitioner argued that they were more qualified and eligible, and the award to the 5th respondent was illegal and arbitrary. They contended that being a registered contractor was not essential for submitting tenders, as per Clause 3. They also argued that the 5th respondent's experience certificate lacked supporting documents, which should have invalidated their bid. Respondents' arguments: The respondents (APCPDCL and the 5th respondent) argued that the petitioner's tender was rightly rejected because they failed to produce a valid wireman permit as required by Clause 7 of the tender specification. They contended that Clause 3 did not specify eligibility criteria but rather instructions for filling schedules, and that the absence of specific stipulations for experience certificate supporting documents did not invalidate the 5th respondent's bid.

Sections Cited

Section 7, Section 3

AI-generated summary — verify with the full judgment below

T- IN THE HIGH COURT OF ANDHRA PRADESH :: AMARAV~' I!4T~" (Special Original Jurisdiction) a ~' TUESDAY, THE TENTH DAY OF OCTOBER ~ • 'j TWO THOUSAND AND TWENTY THREE p - ; ,jJ PRESENT y - THE HONOURABLE SRI JUSTICE RAVI CHEEMALAPATI WRIT PETITION NO: 33999 OF 2022 Between: Vijay Electrical Engineering, Rep. by its Proprietor, R. Bhaskara Rao, Yagnasalapeta, Karamchedu Village and Mandal, Bapatla (old Prakasam) District - 523168. ...Petitioner AND 1. The State of Andhra Pradesh, Rep. by its Principal Secretary, Energy Department, Secretariat, At Velagapudi, Amaravathi, Guntur District.

2.

Andhra Pradesh Central Power Distribution Corporation Ltd., Rep. by its Chairman and Managing Director, Dr.YSR Vidyut Soudha, Having its Corporate Office, Beside Govt. Polytechnic, ITI Road, Vijayawada-520008, NTR (old Krishna) District.

3.

The Chief General Manager (Oand M), O/0. Chairman and Managing Director, Dr.YSR Vidyut Soudha, APCPDCL, Beside Govt. Polytechnic, ITI Road, Vijayawada-520008, NTR (old Krishna) District.

4.

The Superintending Engineer, Operation Circle, APCPDCL, Near Old LTC Building, Ongole, Prakasam District -523001. 5. M.Nagarjuna, S/o. M.Kutumbar

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Andhra Pradesh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.