M/S Vijay Electrical Engineering vs. The State Of Andhra Pradesh
Original PDF →No AI summary yet for this judgment.
Cause title — parties, addresses and appearances
The learned single Judge by virtue of judgment and order impugned, after considering the matter upheld the action of the official respondents, by holding in paragraphs 21 and 22 of the judgment as under:
“21. Clause No.3 is titled, „FILLING OF SCHEDULE‟. It says that Works contract will be awarded to all the registered contractors with valid Grade A Electrical Contractor License and other qualifications specified therein. The said clause further contains that Labour license mentioned therein can be submitted at the time of entering into agreement. A bare reading of this provision makes it clear that it does not contain any mandate that registered contractors alone are eligible to submit tender forms. It only says that work contract will be awarded to the registered contractors. Thus, being a registered contractor is not at all essential for submission of the tender and participation in the tender evaluation process. Therefore, clause-3 of the tender specification did not WA_NO_1222_2023
specify any eligibility criteria. As the title given to it, the said clause only contained some instructions to the tenderers for filling of schedule and nothing more. Thus, the contention of the learned counsel for the petitioner that clause-3 also specifies eligibility criteria is far-fetched.
As per clause-7 which deals with Eligibility for Man Power Supply on Out sourcing, the contractor shall have supervision and Wireman permit holders. The material placed on record shows that the wireman permit produced by the petitioner in relation to one R.Bala Krishna stood expired on 14.07.2021 and it was not revalidated as per the procedure. Thus, the authorities have placed the tender of the petitioner out of consideration for non-fulfilment of the essential and mandatory conditions of the tender notification.”
The learned single Judge accordingly dismissed the writ petition by holding that the petitioner failed to produce the documents as were required to meet the eligibility criteria as per Clause 7 of the tender specification and that the decision of the respondents could not be termed as arbitrary, irrational or mala fide or contrary to law.
We had directed the official respondents to produce, for our perusal the relevant records pertained to the allotment of the contract in question, however, relevant record which was most pertinent with regard to the committee‟s report, which is stated to have been submitted on 22.09.2022 was not produced. WA_NO_1222_2023
We have heard learned counsel for the parties and gone through the relevant records.
It appears to us to be quite clear that apart from the eligibility conditions prescribed under Clause 7 of the tender document envisaging the availability of a supervisor and two wireman, the condition with regard to the contractor being registered with APSPDCL/APCPDCL/APEPDCL was also a condition of eligibility which had to be fulfilled by respondent No.5, with a view to make the said respondent eligible in terms of the tender document. A reference to Clause 3 of the tender document would show that it was only the condition of possession of a labour licence from the Deputy Commissioner/Assistant Commissioner of Labour of the Engineering Works1, the Apex Court in paragraph 6 held:
"
It is true that in submitting its tender accompanied by a cheque of the Union Bank of India and not of the State Bank clause 6 of the tender notice was not obeyed literally, but the question is as to whether the said non-compliance deprived the Diesel Locomotive Works of the authority to accept the bid. As a matter of general proposition it cannot be held that an authority inviting tenders is bound to give effect to every term mentioned in the notice in meticulous detail, and is not entitled to waive even a technical irregularity of little or no significance. The requirements in a tender notice can be classified into two categories - those which lay down the essential conditions of eligibility and the others which are merely ancillary or subsidiary with the main object to be achieved by the condition. In the first case the authority issuing the tender may be required to enforce them rigidly. In the other cases it must be open to the authority to deviate from and not to insist upon the strict literal compliance with the condition in appropriate cases.”
Services Ltd. and others2, the Apex Court held:
“66. We are also not shutting our eyes towards the new principles of judicial review which are being developed; but the law as it stands
1 (1991) 3 SCC 273 2 (2006) 11 SCC 548 WA_NO_1222_2023
now having regard to the principles laid down in the aforementioned decisions may be summarised as under: (i) if there are essential conditions, the same must be adhered to; (ii) if there is no power of general relaxation, ordinarily the same shall not be exercised and the principle of strict compliance would be applied where it is possible for all the parties to comply with all such conditions fully; (iii) if, however, a deviation is made in relation to all the parties in regard to any of such conditions, ordinarily again a power of relaxation may be held to be existing; (iv) the parties who have taken the benefit of such relaxation should not ordinarily be allowed to take a different stand in relation to compliance with another part of tender contract, particularly when he a was also not in a position to comply with all the conditions of tender fully, unless the court otherwise finds relaxation of a condition which being essential in nature could not be relaxed and thus the same was wholly illegal and without juri iction; (v) when a decision is taken by the appropriate authority upon due consideration of the tender document submitted by all the tenderers on b their own merits and if it is ultimately found that successful bidders had in fact substantially complied with the purport and object for which essential conditions were laid down, the same may not ordinarily be interfered with; (vi) the contractors cannot form a cartel. If despite the same, their bids are considered and they are given an offer to match with the rates C quoted by the lowest tenderer, public interest would be given priority; (vii) where a decision has been taken purely on public interest, the court ordinarily should exercise judicial restraint.” WA_NO_1222_2023
issues held:
“16. It is clear even on a reading of this judgment that the words used in the tender document cannot be ignored or treated as redundant or superfluous-they must be given meaning and their necessary significance. Given the fact that in the present case, an essential tender condition which had to be strictly complied with was not so complied with, the appellant would have no power to condone lack of such strict compliance. Any such condonation, as has been done in the present case, would amount to perversity in the understanding or appreciation of the terms of the tender conditions, which must be interfered with by a constitutional court.”
In our opinion, the condition with regard to registration under Clause 3 was an essential condition and could not have been waived at all and further that there was no such power vested with the authority to relax such a condition, much less could an agreement have been executed with the said respondent No.5 on that account.
The rejection of the bid of the petitioner also appears to us to be unwarranted. The basis for the rejection of the bid of the petitioner is that the certificate of wireman permit in regard to 3 (2020) 17 SCC 577 WA_NO_1222_2023
Sri R. Balakrishna, stood expired on 14.07.2021 and was not revalidated.
On the other hand, it can be seen from the record that form-F issued by the Andhra Pradesh Electrical Licensing Board in favour of Sri R. Balakrishna, that his earlier lapsed permit contained permit No.302766 for which a new permit bearing No.307617 was issued which was revalidated from 14.12.2020 to 13.12.2025. 16. Although, the learned single Judge has observed in the judgment and order impugned that the revalidation was not as per the procedure, yet no reasons have been reflected as to what was the procedure for revalidation, which was not followed before such a validation was affected in favour of Sri R. Balakrishna.
On the other hand, it is not even the case of the official respondents that there was validation but not as per the prescribed procedure.
Be that as it may, we hold that the decision in rejecting the bid of the petitioner as also to allot the contract in favour of respondent No.5 was arbitrary and is, accordingly, set aside. The respondents are directed to consider the bid of the petitioner as responsive and take steps accordingly. WA_NO_1222_2023
The judgment and order impugned is, accordingly, set aside and the writ appeal is allowed. No order as to costs.
Pending miscellaneous applications, if any, shall stand closed.
DHIRAJ SINGH THAKUR, CJ R. RAGHUNANDAN RAO, J
SSN WA_NO_1222_2023
HON‟BLE MR.JUSTICE DHIRAJ SINGH THAKUR, CHIEF JUSTICE & HON‟BLE MR. JUSTICE R. RAGHUNANDAN RAO
WRIT APPEAL No.1222 of 2023 DATE : 04.01.2024
SSN
Reproduced from the public record of the Andhra Pradesh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.