Y V Chowdary vs. The State Of Ap

WP/22824/2024HC Andhra PradeshGSTCNR APHC01043954202420 October 2024Bench: B S BHANUMATHI3 pages
For Petitioner: PONNADA SREE VYASFor Respondent: GP FOR IRRI AND CAD, GP FOR FINANCE PLANNING
AI SummaryAllowed

Held

The Court allowed the writ petition. It directed the respondents to release the total amount of Rs. 4,23,043/- to the petitioner. The Court also directed the release of Rs. 22,197/-, if the petitioner was entitled to it, or the higher amount the petitioner was entitled to. Furthermore, the Court ordered the payment of interest as per the entitlement, referencing the judgment of the Division Bench of the High Court in Writ Appeal No.724 of 2021 and batch of cases dated 12.10.2023. This payment was to be made within two months of receiving a copy of the order. The Court clarified that it was open to the petitioner to pursue their claim for a higher rate of interest before an appropriate forum. The issue of the exact quantum of GST and its impact on the final payable amount, beyond what was acknowledged in the written instructions, was not expressly decided, but the direction was to release the admitted amounts and interest.

Facts

The petitioner, Y V Chowdary, filed a writ petition seeking release of payment for works executed under agreement No. 15KW/2022-23. The petitioner claimed an amount of Rs. 4,23,043/- for O and M Repairs for weed removal in various channels. The petitioner contended that despite admission of entitlement, payment was not released, which was arbitrary. The respondents, represented by the Government Pleader for Irrigation, admitted the claim and stated that the value of work done was Rs. 4,45,960/-, including GST of Rs. 47,781/-. They attributed the non-payment to a non-availability of funds and assured payment upon release of funds. The court noted a discrepancy between the petitioner's claimed amount and the gross amount stated by the respondents.

Key Issues

1. Whether the respondents' action in withholding payment for works executed by the petitioner is illegal, arbitrary, and violative of Articles 14 and 21 of the Constitution of India, concerning the non-release of Rs. 4,23,043/-. 2. Whether the petitioner is entitled to interest on the delayed payment. Petitioner's Arguments: The petitioner argued that the non-payment of admitted dues was arbitrary and high-handed, warranting judicial interference. They sought the release of Rs. 4,23,043/- along with interest. Respondents' Arguments: The respondents, through the Government Pleader, admitted the petitioner's claim and the value of work done. They attributed the delay in payment to the non-availability of funds and assured that payment would be made once funds were released. They did not explicitly argue against the entitlement to interest but stated that payment would be made upon fund availability.

Sections Cited

None explicitly mentioned as being discussed or interpreted, though GST is mentioned in the context of the work value.

AI-generated summary — verify with the full judgment below

Cause title — parties, addresses and appearances
APHC010439542024 IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) [3311] MONDAY ,THE TWENTY FIRST DAY OF OCTOBER TWO THOUSAND AND TWENTY FOUR PRESENT THE HONOURABLE MS JUSTICE B S BHANUMATHI WRIT PETITION NO: 22824/2024 Between: Y V Chowdary ...PETITIONER AND The State of A.P and Others ...RESPONDENT(S) Counsel for the Petitioner: 1. PONNADA SREE VYAS Counsel for the Respondent(S): 1. GP FOR IRRI AND CAD 2. GP FOR FINANCE PLANNING The Court made the following:

O R D E R: This writ petition is filed seeking the following relief: “to issue a WRIT OF MANDAMUS or any other appropriate writ or direction declaring the action of the respondents in not releasing the payments for the works vide agreement No. 15KW/2022-23 for contract i.e., O and M Repairs for the Removal of Weed Growth in Poondia channel, Ramanappa channel, Appikatla channel and other branches as illegal, arbitrary and violative of Art 14 and 21 of Constitution of India and consequently direct the respondent authorities to release Rs. 4,23,043/- forthwith for the above referred works executed by the petitioner along with interest for delayed p

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Andhra Pradesh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.