Manasa Constructions vs. The State Of Andhra Pradesh
Held
The Court allowed the writ petition. It directed the respondents to release the amount of Rs. 19,89,942/- to the petitioner within two months from the date of receipt of the order. The Court also directed that the petitioner be paid interest as per their entitlement, referencing a Division Bench judgment in Writ Appeal No. 724 of 2021 and batch cases dated 12.10.2023. The Court clarified that if the petitioner is entitled to a higher amount, that shall also be paid. The petitioner was given the liberty to agitate any claim for a higher rate of interest before an appropriate forum. The Court made no order as to costs.
Facts
The petitioner, Manasa Constructions, filed a writ petition seeking a direction to the respondents (State of Andhra Pradesh and others) to release the final bill amount of Rs. 19,89,942/-, which includes GST of Rs. 4,44,406/-, for O & M works under an irrigation department agreement (Agreement No. 106/2023-24, dated 16-03-2024). The petitioner contended that despite the completion of the work and admission of entitlement by the respondents, the payment was withheld, causing financial loss. The respondents, through the learned Government Pleader for Irrigation, admitted the claim but stated that the bills were not uploaded in CFMS due to a lack of LOC (Letter of Credit) and assured payment upon its release. The court noted a discrepancy between the petitioner's claimed amount and the gross amount payable mentioned in the instructions.
Key Issues
1. Whether the inaction of the respondents in releasing the final bill amount of Rs. 19,89,942/- to the petitioner, despite the completion of work and admitted entitlement, is illegal, arbitrary, and violative of Articles 14, 16, and 21 of the Constitution of India? Petitioner's arguments: The petitioner argued that the non-payment of the admitted amount is arbitrary and high-handed, necessitating judicial intervention. They sought a direction for the immediate release of the final bills and interest. Respondents' arguments: The learned Government Pleader for Irrigation admitted the petitioner's claim but explained that the delay in payment was due to the non-uploading of bills in CFMS owing to a lack of LOC. They assured that payment would be made promptly after the release of the LOC and prayed for appropriate orders.
AI-generated summary — verify with the full judgment below
Cause title — parties, addresses and appearances
The Court made the following Order:
This writ petition is filed seeking the following relief:
“…to issue an appropriate Writ, Order or direction more particularly one in the nature of Writ of Mandamus declare the inaction on part of the respondents herein not releasing the final bill amount worth of Rs.19,89,942/-, Amount Rs.15,45,536/-, along with GST of Rs.4,44,406/-, vide its Agreement No.106/2023-24, Dt:16-03-2024, with interest of execution of completion of O & M works under irrigation department as per agreement, to the petitioner till today and 2 W.P.No.18108 of 2024
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Andhra Pradesh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.