Srihari Constructions vs. The State Of Andhra Pradesh
Held
The High Court allowed the writ petition. The Court directed the respondents to release the EMD & FSD amount of Rs. 3,72,439/- to the petitioner within two months from the date of receiving a copy of the order. The Court also stated that if the petitioner was entitled to any higher amount, it should also be paid as per their entitlement. The Court did not grant any order as to costs. The reasoning for allowing the petition was based on the admission by the respondents regarding the petitioner's entitlement to the EMD and FSD, despite their contention that the specific issue of returning withheld deposits was not covered by the cited judgment on delayed final bill payments. The operative direction was the release of the specified amount within a stipulated timeframe.
Facts
The petitioner, Srihari Constructions, filed a writ petition seeking the return of Earnest Money Deposits (EMD) and Full Security Deposits (FSD) along with Goods and Services Tax (GST) and interest on works executed under the "Neeru Chettu" scheme. The petitioner claimed non-payment of these amounts was illegal and arbitrary. The works were executed under five agreements, all dated November 30, 2018. The respondents, represented by the learned Assistant Government Pleader, admitted the petitioner's claim but stated that the return of withheld deposits did not fall under the ambit of a previous judgment (W.A.No.724 of 2021) concerning delayed payment of final bills. They clarified that FSD is payable after the defect liability period, not from the date of submitting the final bill. The total net amount payable was Rs. 68,81,193, with EMD & FSD amounting to Rs. 3,72,439.
Key Issues
1. Whether the respondents are legally obligated to return the EMD and FSD amounts to the petitioner, along with GST and interest, for works executed under the "Neeru Chettu" scheme. 2. Whether the non-payment of EMD and FSD, as claimed by the petitioner, constitutes an arbitrary and high-handed action by the respondents. Petitioner's Contentions: The petitioner argued that the respondents' failure to return the EMD and FSD, along with GST and interest, was illegal, arbitrary, and violated principles of natural justice and Articles 14, 19(1)(g), and 21 of the Constitution of India. They also cited GO MS No. 266 dated 15.02.2021, memo No.1279341/FMU-WR.I/2020 dated 18.02.2021, and orders in W.A.No.724 of 2021. The petitioner contended that the respondents admitted entitlement to the amounts, making the non-payment unjustified. Respondents' Contentions: The respondents, through the learned Assistant Government Pleader, admitted the petitioner's claim regarding the amount but argued that the case of returning withheld deposits did not fall within the scope of W.A.No.724/2021, which dealt with delayed payment of final bills. They asserted that FSD is payable only after the satisfactory completion of the defect liability period, not from the date of preferring the final bill.
AI-generated summary — verify with the full judgment below
Cause title — parties, addresses and appearances
ORDER:
This writ petition is filed seeking the following relief:
“…to issue a writ, order or direction more particularly one in the nature of Writ of Mandamus declaring the action of the Respondents in not returning the EMD's and FSD's along with GST total and also not paying the interest in respect of works done by the petitioner from the date of submitting bill to final payment payable to the petitioner in relation to the execution of works under the scheme of "Neeru Chettu" i.e., vide Agreement No.31/2018-19, dated 30-11-2018, Agreement No.33/2018-2019, dated 30.11.2018, Agreement No.34/2018-19, dated 30.11.2018, Agreement No.35/2018-19, date
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Andhra Pradesh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.