Sru Datta Sai Constructions vs. The State Of Ap

WP/11359/2024HC Andhra PradeshGSTCNR APHC01022559202416 September 2025Bench: K SREENIVASA REDDY10 pages
AI SummaryPartly Allowed

Held

The Court held that there was no dispute regarding the execution of the work and the amount due to the petitioner. Citing the principle established in WP No. 29077 of 2018, the Court directed the respondents to release the pending amount of Rs. 1,96,77,448/- to the petitioner within twelve weeks from the date of receipt of a copy of the order. The Court further stipulated that if the payment is not made within the specified period, the petitioner would be entitled to claim interest at 6% per annum from the date of the order until realization. The writ petition was disposed of with these directions, and no order as to costs was made.

Facts

The petitioner, Sri Datta Sai Constructions, filed a writ petition seeking a declaration that the respondents' action in withholding a part bill payment of Rs. 1,96,77,448/- for construction works is illegal and arbitrary. The petitioner entered into an agreement with the 4th respondent on February 2, 2022, for the construction of a Center for Excellence for Girls. The petitioner completed the works within the stipulated time, incurring interest on borrowed funds. The total executed work amounted to Rs. 3,15,17,038/- (excluding GST, seigniorage, QC charges, and price escalation), with Rs. 1,18,39,590/- already paid. The remaining balance is Rs. 1,96,77,448/-. A counter affidavit filed by the 8th respondent confirmed the work execution and bill processing, stating that the 3rd, 4th, and 5th bills totaling Rs. 1,96,77,448/- are pending due to revised work entrustment and working estimate approval, with funds yet to be received from the government.

Key Issues

1. Whether the action of the respondents in withholding the part bill amount of Rs. 1,96,77,448/- to the petitioner, despite the admitted execution of works and finalization of bills, is illegal and arbitrary, warranting a direction for its release along with interest, under Article 226 of the Constitution of India? Petitioner's Contention: The petitioner argued that the non-release of the admitted part bill amount is illegal and arbitrary. They relied on a previous order of the High Court in WP No. 29077 of 2018, which directed the respondents to verify and pay undisputed amounts due to the petitioner therein within eight weeks. The petitioner contended that their case is squarely covered by this precedent. Respondents' Contention: The respondents, through their counter affidavit, admitted the execution of works and the processing of bills. However, they cited pending issues related to revised work entrustment and working estimate approval as reasons for the delay in payment, and stated that funds were yet to be received from the government. No specific legal arguments or precedents were cited by the respondents.

AI-generated summary — verify with the full judgment below

. \ 'HC010225592024 IN THE HIGH COURT OF ANDHRA PRADESH £Y AT AMARAVATI (Special Original Jurisdiction) JS i V- m m c® WEDNESDAY,THE SEVENTEENTH DAY OF SEPTEMBEf^^^giHj^ TWO THOUSAND AND TWENTY FIVE PRESENT THE HONOURABLE SRI JUSTICE K SREENIVASA REDDY WRIT PETITION NO: 11359 OF 2024 Between:

1.

Sri Datta Sai Constructions, Rep by its Managing partner, B.B Appa Rao, S/o Pardesi Naidu, Age 59 Yrs, D.No. 4-69-17/1, Law Sons bay Colony, Visakhapatnam. ...Petitioner AND 1. The State Of Andhra Pradesh, Rep. by its principal Secretary, Tribal welfare Department, Secretariat, Velagapudi, Amaravati, A.P.

2.

The State of Andhra Pradesh, Rep. by its Principal Secretary, Finance and Planning Department, Secretariat, Velagapudi, Amaravati, A.P.

3.

The Director of Tribal welfare Department, D.No. 40-6-22A, Kandhari Hotel Road, Revenue Colony, Vijayawada, A.P.

4.

The District Collector and Magistrate, Allurisitaramaraju District (New), A.P

5.

The Project officer Visakhapatnam Dist(old), A.P.

6.

The Engineer in chief, O/o Tribal Welfare engineering Department 40- 1-86, Fortune Murali Park Road, Revenue Colony,Vijayawada A.P.

7.

The Superintending Engineer, O/o Tribal Welfare Department Visakhapat

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Andhra Pradesh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.