M/S.Ashutosh Construction vs. State Of Odisha
Held
The Court noted that the State Government had issued revised guidelines on 10.12.2018, superseding the earlier memorandum dated 07.12.2017, which addressed the grievance of contractors regarding the differential tax amount due to the GST regime. These revised guidelines provided a detailed procedure for determining the GST-inclusive work value for the balance work executed after 30.06.2017, based on the revised Schedule of Rates (SoR-2014) and the tender premium/discount. The guidelines stipulated that if the revised GST-inclusive work value for the balance work exceeded the original agreement work value for that balance work, the works contractor would be reimbursed for the excess amount. Conversely, if it was less, the payment would be reduced, and any excess payment already made would be recovered. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority was directed to consider and dispose of the representation in light of the revised guidelines dated 10.12.2018 as expeditiously as possible, preferably by 31.03.2019. The petitioner was granted the liberty to challenge the authority's decision if aggrieved. No coercive action was to be taken against the petitioner until 31.03.2019.
Facts
The petitioner, a works contractor, filed a writ petition challenging the opposite parties' refusal to reimburse the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) on 01.07.2017. The petitioner also sought to quash Clause 1(iii) of a Finance Department Memorandum dated 07.12.2017. The grievance stemmed from being required to pay GST on contracts entered into before the GST regime, where such tax was not originally envisaged. The State submitted revised guidelines issued on 10.12.2018, superseding the earlier memorandum, which provided a procedure for determining and reimbursing the GST amount for works contracts tendered before 01.07.2017 but executed partly or wholly thereafter.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to 01.07.2017 but executed thereafter, and if so, under what procedure? (Mixed question of law and fact, relating to the interpretation and application of tax laws and contractual terms). Petitioner's contention: The petitioner argued that the introduction of GST created an unforeseen tax liability on contracts where GST was not contemplated at the time of agreement, and therefore, they should be reimbursed for this additional tax burden. Revenue's contention: The learned Additional Government Advocate submitted that the Government had issued revised guidelines on 10.12.2018 to address such issues, superseding the earlier memorandum dated 07.12.2017. These revised guidelines provided a mechanism for calculating and reimbursing the differential GST amount for eligible works contracts.
AI-generated summary — verify with the full judgment below
04.1.2019
Heard learned counsel for the parties.
By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST issued by th
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.