G.Gopal Rao Dora vs. State Of Orissa

WP(C)/18647/2018HC OrissaGSTCNR ODHC01055171201809 January 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA5 pages
AI SummaryRemanded

Held

The Court noted that the State had issued revised guidelines on December 10, 2018, to address the issue of differential tax amounts for works contracts executed after the implementation of GST, where tenders were invited prior to July 1, 2017. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority was then directed to consider and dispose of the representation in light of the aforesaid revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by March 31, 2019. The Court also stated that if the petitioner was aggrieved by the authority's decision, they would be at liberty to challenge it. No coercive action was to be taken against the petitioner until March 31, 2019. The writ petition was disposed of with liberty to file an application for revival within thirty days if any difficulty arose.

Facts

The petitioner, a works contractor, filed a writ petition challenging the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that the introduction of GST resulted in tax liabilities not anticipated when agreements were entered into. The State submitted revised guidelines issued by the Government of Odisha, Finance Department, on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines provided a procedure for determining the GST-inclusive work value for balance work executed after GST implementation, where tenders were invited before July 1, 2017.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly thereafter? (Mixed question of law and fact, turning on the interpretation of contractual terms and the applicability of the GST regime). Petitioner's Contention: The petitioner argued that the introduction of GST created an unforeseen tax burden, necessitating reimbursement of the differential tax amount. The petitioner relied on the principle that contractual obligations should not be adversely affected by subsequent changes in tax law without appropriate adjustments. Revenue's Contention: The State submitted revised guidelines issued by the Finance Department, Government of Odisha, on December 10, 2018. These guidelines provided a detailed procedure for calculating the GST-inclusive work value for balance work and stipulated that contractors would be reimbursed for excess amounts if the revised value exceeded the original agreement value, or payments would be reduced if it was less. The State implicitly argued that the revised guidelines provided the mechanism for addressing the petitioner's grievance.

AI-generated summary — verify with the full judgment below

02.

09.01.2019

Heard Mr. A. Pattnaik, learned counsel for the petitioner and learned Additional Government Advocate for the State- opposite parties.

By way of this writ petition, in substance, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST i

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.