Woodhill Infrastructure Limited vs. State Of Odisha

WP(C)/22901/2018HC OrissaGSTCNR ODHC01065432201809 January 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA5 pages
AI SummaryRemanded

Held

The Court noted that the State had issued revised guidelines on December 10, 2018, to address the issue of works contracts executed after the implementation of GST for tenders invited prior to July 1, 2017. These guidelines outline a procedure to determine the GST-inclusive work value for the balance work, considering the revised Schedule of Rates (SoR-2014) and any tender premium/discount. Crucially, the guidelines stipulate that if the revised GST-inclusive work value for the balance work is more than the original agreement work value for the balance work, the works contractor is to be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, which the authority must consider and dispose of in light of the revised guidelines expeditiously, preferably by March 31, 2019. No coercive action was to be taken against the petitioner until March 31, 2019. The writ petition was disposed of with liberty to the petitioner to seek revival if any difficulty arose.

Facts

The petitioner, a works contractor, challenged the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner argued that GST was not envisaged when the agreements were entered into, leading to an increased tax burden. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines address how to handle works contracts tendered before July 1, 2017, but executed partly or wholly after that date, by providing a procedure to determine the GST-inclusive work value for the balance work and reimbursement for excess amounts.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into before July 1, 2017, but executed after that date? Petitioner's contention: The petitioner argued that the introduction of GST resulted in a tax liability that was not anticipated at the time of entering into the agreements, thus entitling them to reimbursement of the differential tax amount. Revenue/State's contention: The State submitted revised guidelines dated December 10, 2018, which provide a mechanism for determining the GST-inclusive work value for the balance work and for reimbursement of any excess amount if the revised value exceeds the original agreement value. The State relied on these revised guidelines to address the petitioner's grievance.

AI-generated summary — verify with the full judgment below

02.

09.01.2019

Heard Mr. S. S. Padhy, learned counsel for the petitioner and learned Additional Government Advocate for the State- opposite parties.

By way of this writ petition, in substance, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.