M/S.Abs Engineering And Developers vs. State Of Odisha

WP(C)/16970/2018HC OrissaGSTCNR ODHC01050232201809 January 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA5 pages
AI SummaryRemanded

Held

The Court noted that the State had issued revised guidelines on December 10, 2018, to address the specific issue of works contracts entered into before July 1, 2017, but executed thereafter. These guidelines provide a procedure for determining the GST-inclusive work value for the balance work by considering the revised Schedule of Rates (SoR-2014) and applying the tender premium/discount. Crucially, the guidelines stipulate that if the revised GST-inclusive work value for the balance work is more than the original agreement work value for that balance work, the works contractor is to be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by March 31, 2019. The petitioner retains the liberty to challenge the authority's decision if aggrieved. No coercive action is to be taken against the petitioner until March 31, 2019. The writ petition was disposed of with liberty to revive it within thirty days if difficulties arise.

Facts

The petitioner, a works contractor, filed a writ petition challenging the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that they were required to pay GST on contracts entered into before the GST regime, which was not originally envisaged. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines addressed the issue of works contracts tendered before July 1, 2017, but executed partly or wholly after that date, outlining a procedure for determining the GST-inclusive work value for the balance work and reimbursement of excess amounts.

Key Issues

1. Whether the petitioner is entitled to reimbursement of differential tax amounts arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed thereafter? (Mixed question of law and fact, concerning the interpretation and application of tax laws and contractual terms). Petitioner's contention: The petitioner argued that the introduction of GST resulted in an unforeseen tax liability for contracts signed under the previous VAT regime, and they should be compensated for this differential tax amount. Revenue/State's contention: The State submitted revised guidelines dated December 10, 2018, which provided a mechanism for calculating the GST-inclusive work value for the balance work and for reimbursing contractors if the revised value exceeded the original agreement value. The State relied on these revised guidelines as the basis for addressing the petitioner's grievance.

Sections Cited

None explicitly mentioned as being discussed or interpreted in detail, beyond the general context of the GST regime and its impact on works contracts.

AI-generated summary — verify with the full judgment below

03.

09.01.2019

Heard Mr. B.P. Samal, learned counsel for the petitioner and learned Additional Government Advocate for the State- opposite parties.

By way of this writ petition, in substance, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST issu

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.