M/S.P.C.Construction vs. State Of Orissa

WP(C)/19123/2018HC OrissaGSTCNR ODHC01056423201809 January 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA5 pages
AI SummaryRemanded

Held

The Court acknowledged the petitioner's grievance regarding the differential tax amount due to the transition to GST for works contracts. The State presented revised guidelines dated December 10, 2018, which superseded earlier guidelines and outlined a procedure for calculating the GST-inclusive work value for balance work executed after July 1, 2017, where tenders were invited prior to that date. These guidelines stipulated that if the revised GST-inclusive work value for the balance work exceeded the original agreement work value for that balance work, the contractor would be reimbursed for the excess amount. Conversely, if it was less, the payment would be reduced, and any excess payment already made would be recovered. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within four weeks, ventilating their grievance. The authority was instructed to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by March 31, 2019. The Court also stated that if the petitioner remained aggrieved by the authority's decision, they would be at liberty to challenge it. No coercive action was to be taken against the petitioner until March 31, 2019. The writ petition was disposed of with liberty to the petitioner to file an application for revival within thirty days from the order if any difficulty arose.

Facts

The petitioner, a works contractor, filed a writ petition challenging the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that GST was not envisaged when agreements were entered into, leading to an unexpected tax burden. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines provided a procedure for determining the payable amount to works contractors for balance work executed after GST implementation, where tenders were invited before July 1, 2017, based on the pre-GST Schedule of Rates (SoR-2014).

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly after that date? Petitioner's Contention: The petitioner argued that the introduction of GST resulted in an additional tax liability that was not contemplated at the time of entering into the agreements, and therefore, they should be reimbursed for this differential tax amount. Revenue's Contention: The State submitted revised guidelines issued by the Finance Department on December 10, 2018, which provided a mechanism for calculating and potentially reimbursing contractors for the GST impact on balance work executed after the GST regime came into effect. The State relied on these revised guidelines as the basis for addressing the petitioner's grievance.

AI-generated summary — verify with the full judgment below

02.

09.01.2019

Heard Mr. A. Pattnaik, learned counsel for the petitioner and learned Additional Government Advocate for the State- opposite parties.

By way of this writ petition, in substance, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.