J.B.S.Construction PVT.LTD. vs. State Of Odisha
Held
The Court acknowledged the revised guidelines issued by the Government of Odisha, Finance Department, on December 10, 2018, concerning works contracts under GST. These guidelines provide a detailed procedure for calculating the GST-inclusive work value for balance work executed after July 1, 2017, where tenders were invited before that date. The procedure involves ascertaining the work done after June 30, 2017, determining its revised estimated work value as per the Revised SoR-2014, adjusting for tender premium/discount, and then adding the applicable GST rate. Crucially, the guidelines stipulate that if the revised GST-inclusive work value for the balance work is more than the original agreement work value for that balance work, the works contractor is to be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, which the authority must consider and dispose of in light of the revised guidelines by March 31, 2019. No coercive action is to be taken against the petitioner until March 31, 2019. The petitioner retains the liberty to challenge the authority's decision if aggrieved and to seek revival of the writ petition within thirty days from March 31, 2019, if any difficulty arises.
Facts
The petitioner, a works contractor, filed a writ petition challenging the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that they were required to pay GST on contracts entered into before the GST regime, which was not originally envisaged. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines provided a procedure for determining the payable amount to works contractors for balance work executed after July 1, 2017, where tenders were invited before that date based on the pre-revised Schedule of Rates (SoR-2014).
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly thereafter? The petitioner argued that the introduction of GST imposed a tax liability that was not contemplated when the agreements were made, leading to financial hardship. The State contended that revised guidelines had been issued by the Finance Department on December 10, 2018, which provided a mechanism for addressing such claims. These guidelines aimed to clarify how the GST amount should be calculated and reimbursed for balance work executed post-GST implementation, considering the original contract rates and any tender premium or discount. The State relied on the Office Memorandum No. FIN-CTI-TAX-0045-2017/38535/F dated 10.12.2018.
Sections Cited
Not specified
AI-generated summary — verify with the full judgment below
09.01.2019
Heard Mr. P.C. Nayak, learned counsel for the petitioner and learned Additional Government Advocate for the State- opposite parties.
By way of this writ petition, in substance, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST is
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.