Surender Singh Kabi vs. State Of Odisha

WP(C)/17520/2018HC OrissaGSTCNR ODHC01051682201809 January 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA5 pages
AI SummaryRemanded

Held

The Court acknowledged the petitioner's grievance regarding the differential tax amount due to the GST transition. The State presented revised guidelines dated December 10, 2018, which superseded previous guidelines and provided a detailed procedure for works contracts tendered before July 1, 2017, but executed thereafter. These guidelines stipulated how to ascertain the balance work, determine its revised estimated value based on the Revised Schedule of Rates (SoR-2014) excluding embedded taxes, adjust for tender premium/discount, and finally add the applicable GST rate. The guidelines also specified that if the revised GST-inclusive work value for the balance work exceeded the original agreement value, the contractor would be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within four weeks, which would then be considered and disposed of in light of the revised guidelines by March 31, 2019. No coercive action was to be taken against the petitioner until March 31, 2019. The writ petition was disposed of with liberty to revive it within thirty days if difficulties arose.

Facts

The petitioner, a works contractor, challenged the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that the GST liability was not anticipated when entering into agreements, leading to financial difficulty. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines addressed the issue of works contracts tendered before July 1, 2017, but executed partly or wholly after that date, outlining a procedure for determining the payable amount to contractors.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into before July 1, 2017, but executed thereafter? Petitioner's contention: The petitioner argued that the introduction of GST imposed a tax liability not envisaged at the time of entering into agreements, causing financial hardship and necessitating reimbursement of the differential tax amount. State's contention: The State submitted revised guidelines issued by the Finance Department on December 10, 2018, which provided a mechanism for calculating and potentially reimbursing contractors for the additional GST burden on balance works executed after July 1, 2017, for contracts tendered prior to that date. The State relied on these revised guidelines as the basis for addressing the petitioner's grievance.

AI-generated summary — verify with the full judgment below

02.

09.01.2019

Heard Mr. A. Pattnaik, learned counsel for the petitioner and learned Additional Government Advocate for the State- opposite parties.

By way of this writ petition, in substance, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST iss

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.