M/S Sidhi Binayak Infrastructure vs. State Of Odisha
Held
The Court did not directly decide the entitlement to reimbursement but disposed of the writ petition by directing the petitioner to make a comprehensive representation before the appropriate authority within four weeks. This representation should ventilate the petitioner's grievance in light of the revised guidelines dated 10.12.2018 issued by the Finance Department, Government of Odisha. The authority is directed to consider and dispose of the representation expeditiously, preferably by 30.04.2019. The Court stated that if the petitioner is aggrieved by the authority's decision, they are at liberty to challenge it. No coercive action is to be taken against the petitioner until 30.04.2019. The Court also granted liberty to the petitioner to file an application for revival of the writ petition within thirty days from the order if they face any difficulty. The ratio decidendi is that grievances arising from the GST transition for works contracts should be addressed through the prescribed administrative mechanism, and the High Court would intervene if the administrative process fails.
Facts
The petitioner, a works contractor, filed a writ petition challenging the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) on 01.07.2017. The petitioner's grievance was that they were required to pay GST on works contracts entered into before the GST regime, which was not anticipated in the original agreements. The State submitted revised guidelines issued by the Finance Department on 10.12.2018, superseding earlier guidelines from 07.12.2017, to address issues related to works contracts under GST for tenders invited prior to 01.07.2017 but executed partly or wholly thereafter.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into before 01.07.2017 but executed thereafter? (Question of law) Petitioner's contention: The petitioner argued that the introduction of GST resulted in an increased tax liability not envisaged at the time of entering into the agreements, and therefore, they should be reimbursed for this differential tax amount. The petitioner relied on the principle that contractual obligations should not be adversely affected by subsequent legislative changes without adequate provision for compensation. Revenue/State's contention: The State submitted revised guidelines issued by the Finance Department on 10.12.2018, which provided a procedure for determining the GST-inclusive work value for the balance work executed after 01.07.2017. These guidelines outlined how to ascertain the work value as per the revised Schedule of Rates (SoR-2014), apply tender premium/discount, and add the applicable GST rate. The State contended that these guidelines provided a mechanism for addressing the petitioner's grievance.
Sections Cited
Section 73, Section 129, Rule 86A
AI-generated summary — verify with the full judgment below
22.01.2019
Heard Mr. Jashobanta Dash, learned counsel for the petitioner and learned Additional Government Advocate for the State-opposite parties.
By way of this writ petition, in substance, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guidelines relating to
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.