M/S.Sidhi Binayak Infrastructure vs. State Of Odisha

WP(C)/193/2019HC OrissaGSTCNR ODHC01000792201922 January 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA5 pages
AI SummaryRemanded

Held

The Court acknowledged the petitioner's grievance regarding the differential tax amount arising from the transition to GST for works contracts executed after July 1, 2017, where tenders were invited prior to that date. The Court noted the State's submission of revised guidelines issued on December 10, 2018, which provide a detailed procedure for calculating the GST-inclusive work value for the balance work. These guidelines aim to address the contractors' claims for additional GST amounts by revising the work value based on the pre-GST SoR-2014 and then adding the applicable GST. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation expeditiously, preferably by April 30, 2019, in light of the revised guidelines. The petitioner retains the liberty to challenge the authority's decision if aggrieved. No coercive action is to be taken against the petitioner until April 30, 2019. The writ petition was disposed of with liberty to revive it within thirty days if difficulties arise.

Facts

The petitioner, a works contractor, challenged the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that the GST liability was not anticipated when entering into agreements based on the pre-GST Schedule of Rates (SoR-2014). The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines provide a procedure for determining the GST-inclusive work value for balance work executed after GST implementation, where tenders were invited before July 1, 2017, on the basis of SoR-2014. The court directed the petitioner to make a representation to the appropriate authority based on these revised guidelines.

Key Issues

1. Whether the petitioner is entitled to reimbursement of differential tax amounts due to the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly thereafter? Petitioner's contention: The petitioner argued that the introduction of GST imposed a tax liability that was not envisaged at the time of entering into the agreements, leading to a financial burden. They sought reimbursement of this differential tax amount. Revenue/State's contention: The State submitted revised guidelines issued on December 10, 2018, which provide a mechanism for calculating the GST-inclusive work value for balance work executed after GST implementation. This procedure aims to address the claims of contractors for additional amounts towards GST. The State relied on the Office Memorandum No. FIN-CTI-TAX-0045-2017/38535/F dated 10.12.2018.

AI-generated summary — verify with the full judgment below

02.

22.01.2019

Heard Mr. Jashobanta Dash, learned counsel for the petitioner and learned Additional Government Advocate for the State-opposite parties.

By way of this writ petition, in substance, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guidelines relating to

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.