Jyotin Kumar Sahoo vs. The Dy.Chief Elect.Engineer (Con-Ii),East Coast Railway,Bbsr

WP(C)/429/2019HC OrissaGSTCNR ODHC01001467201922 January 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court acknowledged the issue faced by contractors due to the change in tax regime. It noted that the State had issued revised guidelines on 10.12.2018 to address such grievances. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority was then directed to consider and dispose of the representation in light of the revised guidelines dated 10.12.2018, as expeditiously as possible, preferably by 30.04.2019. The Court also stated that if the petitioner was aggrieved by the authority's decision, they would be at liberty to challenge it. No coercive action was to be taken against the petitioner until 30.04.2019. The writ petition was disposed of with these directions.

Facts

The petitioner, a works contractor, filed a writ petition challenging the opposite parties' action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) on 01.07.2017. The petitioner's grievance was that they were required to pay GST on works contracts entered into before the GST regime, which was not envisaged in the original agreements. The State submitted revised guidelines issued by the Government of Odisha, Finance Department, on 10.12.2018, which superseded earlier guidelines dated 07.12.2017. These revised guidelines provided a procedure for determining the GST-inclusive work value for balance work executed after 01.07.2017, based on tenders invited before that date.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to 01.07.2017 but executed partly or wholly thereafter? Petitioner's contention: The petitioner argued that the introduction of GST led to an increased tax burden not contemplated at the time of entering into the agreements, and they should be compensated for this differential tax amount. They relied on the principle that contractual obligations should not be adversely affected by subsequent legislative changes without a mechanism for adjustment. Revenue/State's contention: The State submitted revised guidelines issued by the Finance Department on 10.12.2018, which provided a detailed procedure for calculating the GST-inclusive work value for balance work. This procedure aimed to address the claims of contractors for additional amounts towards GST on works executed after the GST implementation, based on tenders invited before 01.07.2017.

Sections Cited

Not specified

AI-generated summary — verify with the full judgment below

02.

22.01.2019

Heard learned counsel for the parties.

By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN-C

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.