M/S. D.D.Builders LTD. vs. State Of Odisha

WP(C)/1262/2019HC OrissaGSTCNR ODHC01003526201925 January 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE BISWAJIT MOHANTY4 pages
AI SummaryRemanded

Held

The Court noted that the State Government had issued revised guidelines on December 10, 2018, in supersession of the earlier memorandum dated December 7, 2017. These revised guidelines provide a detailed procedure for determining the GST-inclusive work value for the balance work in contracts where tenders were invited before July 1, 2017, but payments were made after the GST implementation. The guidelines stipulate that if the revised GST-inclusive work value for the balance work is more than the original agreement work value for the balance work, the works contractor is to be reimbursed for the excess amount. Conversely, if it is less, the payment is to be reduced, and any excess payment already made is to be recovered. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, expeditiously, preferably by April 30, 2019. No coercive action was to be taken against the petitioner until April 30, 2019. The writ petition was disposed of with liberty to the petitioner to challenge the authority's decision if aggrieved.

Facts

The petitioner, a works contractor, filed a writ petition challenging the action of the opposite parties (State authorities) for not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner also sought to quash Clause 1(iii) of the Finance Department Memorandum dated December 7, 2017. The grievance was that the GST liability was not envisaged when the agreements were entered into. The State submitted revised guidelines dated December 10, 2018, superseding the earlier memorandum, to address issues related to works contracts under GST for tenders invited before July 1, 2017, but executed partly or wholly after that date.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into before July 1, 2017, but executed thereafter? (Question of law) 2. Whether Clause 1(iii) of the Finance Department Memorandum dated December 7, 2017, which allegedly caused the grievance, is liable to be quashed? (Question of law) Petitioner's contention: The petitioner argued that due to the introduction of GST, they are required to pay tax that was not anticipated at the time of entering into the agreements, leading to a financial burden. They sought reimbursement of this differential tax amount. Revenue's contention: The Additional Government Advocate submitted that revised guidelines were issued by the Government of Odisha, Finance Department, on December 10, 2018, which superseded the earlier guidelines of December 7, 2017. These revised guidelines provide a procedure for determining the amount payable to works contractors in cases where tenders were invited before July 1, 2017, but payments for the balance work were made after the implementation of GST.

Sections Cited

Section 73, Section 129, Rule 86A

AI-generated summary — verify with the full judgment below

02.

25.01.2019

Heard learned counsel for the parties.

By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guidelines relating to works contract

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.