Gourav Construction vs. State Of Odisha
Held
The Court noted that the Government of Odisha, Finance Department, had issued revised guidelines on December 10, 2018, in supersession of the earlier memorandum dated December 7, 2017. These revised guidelines address the issue of works contracts entered into before July 1, 2017, but executed thereafter. The procedure outlined in the revised guidelines involves determining the revised estimated work value for the balance work as per the Revised SoR-2014, applying tender premium/discount, adding the applicable GST rate, and then determining the GST-inclusive work value. If this revised value is more than the original agreement value for the balance work, the contractor is to be reimbursed. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, expeditiously, preferably by April 30, 2019. No coercive action is to be taken against the petitioner until April 30, 2019. The writ petition was disposed of with liberty to the petitioner to challenge the authority's decision if aggrieved.
Facts
The petitioner, a works contractor, filed a writ petition challenging the action of the opposite parties (revenue/State) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner also sought to quash Clause 1(iii) of the Finance Department Memorandum dated December 7, 2017. The grievance was that the introduction of GST necessitated paying tax not originally envisaged in the agreements. The Additional Government Advocate submitted revised guidelines issued by the Government of Odisha, Finance Department, on December 10, 2018, superseding the earlier memorandum.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly after that date? 2. Whether Clause 1(iii) of the Finance Department Memorandum dated December 7, 2017, which allegedly caused the grievance, should be quashed? Petitioner's Contention: The petitioner argued that due to the introduction of GST, they are required to pay tax that was not contemplated when the agreements were entered into, leading to a financial burden. Revenue/State's Contention: The revenue/State submitted revised guidelines dated December 10, 2018, which provide a procedure for determining the GST-inclusive work value for the balance work and reimbursement of excess amounts to contractors, superseding the earlier memorandum.
Sections Cited
Section 1(iii) of Finance Department Memorandum dated 07.12.2017, Finance Department Office memorandum No. FIN-CTI-TAX-0045-2017/38535/F Dated 10.12.2018
AI-generated summary — verify with the full judgment below
25.01.2019
Heard learned counsel for the parties.
By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guidelines relating to works contract
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.