G.Gopal Rao Dora vs. State Of Odisha

WP(C)/18818/2018HC OrissaGSTCNR ODHC01055701201830 January 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court noted that the State Government had issued revised guidelines on December 10, 2018, to address the issue of works contracts executed across the VAT-GST transition. These guidelines provided a mechanism for calculating the GST-inclusive work value for the balance work performed after July 1, 2017. The procedure involves ascertaining the work done after June 30, 2017, determining its revised estimated work value as per the Revised SoR-2014, adjusting it by the tender premium/discount, and then adding the applicable GST. The guidelines clearly state that if this revised GST-inclusive work value is more than the original agreement work value for the balance work, the contractor is to be reimbursed for the excess amount. Conversely, if it is less, the payment is to be reduced, and any excess payment already made is to be recovered. The Court directed the petitioner to make a comprehensive representation to the appropriate authority, which would then consider and dispose of the representation in light of these revised guidelines by March 31, 2019. The Court also granted liberty to the petitioner to challenge the authority's decision if aggrieved and ordered that no coercive action would be taken against the petitioner until March 31, 2019.

Facts

The petitioner, a works contractor, filed a writ petition challenging the action of the opposite parties (State) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective from July 1, 2017. The petitioner's grievance was that they were required to pay GST on works contracts entered into before the GST regime, which was not envisaged in the original agreements. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines addressed the issue of additional GST claims by contractors for works tendered before July 1, 2017, but executed partly or wholly after that date.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed thereafter? Petitioner's contention: The petitioner argued that the introduction of GST required them to pay tax that was not contemplated when the agreements were made, thus causing financial hardship. They sought reimbursement for this additional tax burden. Revenue's contention: The Revenue submitted revised guidelines issued by the Government of Odisha, Finance Department, on December 10, 2018. These guidelines provided a procedure for determining the GST-inclusive work value for the balance work executed after July 1, 2017, and stipulated that contractors would be reimbursed if the revised value exceeded the original agreement value, or face recovery if it was less. The Revenue relied on these revised guidelines.

AI-generated summary — verify with the full judgment below

02.

30.01.2019

Heard learned counsel for the parties.

By way of this writ petition, in substance, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN-CTI-TAX

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.