M/S Judhisthira Parida And Co. vs. State Of Odisha
Held
The Court noted that the State had issued revised guidelines on December 10, 2018, to address the issue of works contracts where tenders were invited before July 1, 2017, but execution continued into the GST regime. These guidelines provide a detailed procedure for calculating the GST-inclusive work value for the balance work, considering the original agreement rates based on the pre-revised Schedule of Rates (SoR-2014) and then applying the revised SoR-2014 and tender premium/discount. The guidelines stipulate that if the revised GST-inclusive work value for the balance work exceeds the original agreement work value for that balance work, the contractor is to be reimbursed for the excess amount. Conversely, if it is less, the payment is to be reduced, and any excess payment already made is to be recovered. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, expeditiously, preferably by April 30, 2019. The Court also granted liberty to the petitioner to challenge the authority's decision if aggrieved and ordered that no coercive action would be taken against the petitioner until April 30, 2019.
Facts
The petitioner, a works contractor, filed a writ petition challenging the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that they were required to pay GST on works contracts entered into before the GST regime, which was not originally envisaged in their agreements. The State, through the Additional Government Advocate, submitted revised guidelines issued by the Government of Odisha, Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines addressed the issue of additional GST claims by contractors for works tendered before July 1, 2017, but executed partly or wholly after that date.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed thereafter? (Question of law) Petitioner's contention: The petitioner argued that the introduction of GST necessitated paying tax that was not contemplated when the agreements were finalized, thus entitling them to reimbursement of this additional tax burden. They relied on the principle that contractual obligations should not be unilaterally altered to the detriment of one party due to a change in tax laws. Revenue/State's contention: The State submitted revised guidelines issued by the Finance Department on December 10, 2018, which provided a procedure for determining and reimbursing GST-inclusive work values for balance work executed after July 1, 2017, for contracts tendered before that date. They argued that these guidelines offered a mechanism to address the petitioner's grievance.
Sections Cited
Not specified
AI-generated summary — verify with the full judgment below
06.02.2019
Heard learned counsel for the parties.
By way of this writ petition, in substance, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN-CTI
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.