Tulasee Construction vs. State Of Orissa

WP(C)/21318/2018HC OrissaGSTCNR ODHC01061921201812 February 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court did not directly rule on the validity of Clause 6 of the earlier memorandum. Instead, it acknowledged the revised guidelines issued by the Finance Department on 10.12.2018, which provided a comprehensive framework for addressing the issue of GST on works contracts executed post-GST, for tenders issued pre-GST. The Court directed the petitioner to make a representation to the appropriate authority within four weeks, ventilating their grievances in light of these revised guidelines. The authority was directed to consider and dispose of the representation expeditiously, preferably by April 30, 2019. The Court also stated that if the petitioner remained aggrieved by the authority's decision, they would be at liberty to challenge it. No coercive action was to be taken against the petitioner until April 30, 2019. The Court expressly left undecided the ultimate outcome of the petitioner's claim pending the authority's decision.

Facts

The petitioner, a works contractor, filed a writ petition challenging the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner argued that the GST liability was not anticipated when agreements were entered into. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines address how to handle works contracts tendered before July 1, 2017, but executed partly or wholly after that date, particularly concerning the calculation of GST on the balance work. The Court directed the petitioner to make a representation based on these revised guidelines.

Key Issues

1. Whether Clause 6 of the Finance Department Memorandum dated 22.07.2017 is arbitrary, unfair, and unreasonable in the context of works contracts executed after the implementation of GST. Petitioner's Contention: The petitioner argued that the introduction of GST created a tax liability that was not envisaged at the time of entering into the agreements, leading to financial hardship. They sought reimbursement of the differential tax amount. Revenue's Contention: The Revenue submitted revised guidelines dated 10.12.2018, which provided a detailed procedure for calculating GST on the balance work for contracts tendered before July 1, 2017, but executed thereafter. These guidelines aimed to address the grievances of contractors by providing a mechanism for determining the revised GST-inclusive work value and making appropriate adjustments, including reimbursement if the revised value exceeded the original agreement value.

AI-generated summary — verify with the full judgment below

02.

12.02.2019

By way of this writ petition, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to declare Clause 6 of the Finance Department Memorandum dated 22.07.2017 as arbitrary, unfair and unreasonable.

Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST issued by

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.