Tulasee Construction vs. State Of Orissa

WP(C)/21310/2018HC OrissaGSTCNR ODHC01061886201812 February 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court did not directly decide the core issue of the State's obligation to reimburse the differential tax amount. Instead, it directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority is then mandated to consider and dispose of this representation in light of the revised guidelines issued by the Finance Department on December 10, 2018. The court specified that this disposal should be done expeditiously, preferably by April 30, 2019. The petitioner retains the liberty to challenge the decision of the authority if they remain aggrieved. No coercive action is to be taken against the petitioner until April 30, 2019. The court expressly left undecided the ultimate determination of the reimbursement amount and the validity of the initial memorandum.

Facts

The petitioner, a contractor, filed a writ petition challenging the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner argued that GST was not envisaged when agreements were entered into, leading to an unexpected tax burden. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding previous guidelines from December 7, 2017. These revised guidelines provided a procedure for determining the GST-inclusive work value for balance work executed after July 1, 2017, on contracts tendered before that date based on the Schedule of Rates – 2014 (SoR-2014). The court directed the petitioner to make a representation based on these revised guidelines.

Key Issues

1. Whether the State is obligated to reimburse contractors for the differential tax amount arising from the introduction of GST on works contracts entered into prior to July 1, 2017, but executed partly or wholly thereafter. Petitioner's contention: The petitioner argued that the introduction of GST imposed a tax liability that was not contemplated at the time of entering into the agreements, thus necessitating reimbursement of the differential tax amount. The petitioner also sought to declare Clause 6 of the Finance Department Memorandum dated July 22, 2017, as arbitrary and unreasonable. Revenue/State's contention: The State submitted revised guidelines dated December 10, 2018, which provided a mechanism for calculating the GST-inclusive work value for balance work executed after the GST implementation. These guidelines aimed to address the grievances of contractors by allowing for reimbursement of excess amounts if the revised GST-inclusive work value exceeded the original agreement value for the balance work. The State relied on these revised guidelines as a solution to the issue.

Sections Cited

Not specified in the judgment

AI-generated summary — verify with the full judgment below

02.

12.02.2019

By way of this writ petition, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to declare Clause 6 of the Finance Department Memorandum dated 22.07.2017 as arbitrary, unfair and unreasonable.

Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST issued by

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.