Tulasee Construction vs. State Of Orissa

WP(C)/21308/2018HC OrissaGSTCNR ODHC01061883201812 February 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court did not directly decide on the arbitrariness of Clause 6 of the Finance Department Memorandum dated 22.07.2017. Instead, it acknowledged the revised guidelines issued by the Government of Odisha on December 10, 2018, which provided a comprehensive procedure for determining the GST-inclusive work value for balance work on contracts tendered before July 1, 2017. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievances. The authority was then instructed to consider and dispose of this representation in light of the aforesaid revised guidelines dated 10.12.2018, as expeditiously as possible, preferably by April 30, 2019. The Court also stated that if the petitioner remained aggrieved by the authority's decision, they would be at liberty to challenge it. No coercive action was to be taken against the petitioner until April 30, 2019. The issue of reimbursement of differential tax was thus deferred for consideration by the administrative authority based on the new guidelines.

Facts

The petitioner, a works contractor, challenged the action of the opposite parties (State authorities) in not reimbursing the differential tax amount arising from the transition of the tax regime from Value Added Tax (VAT) to Goods and Services Tax (GST) effective from July 1, 2017. The petitioner argued that the GST liability was not envisaged when agreements were entered into based on the pre-GST regime. The State submitted revised guidelines issued on December 10, 2018, superseding earlier guidelines from December 7, 2017, to address the difficulties faced by contractors regarding works contracts under GST. These revised guidelines provided a procedure for determining the GST-inclusive work value for balance work executed after July 1, 2017, on contracts tendered before that date.

Key Issues

1. Whether Clause 6 of the Finance Department Memorandum dated 22.07.2017 is arbitrary, unfair, and unreasonable in the context of works contracts executed under the GST regime. 2. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly thereafter. Petitioner's Contention: The petitioner argued that the introduction of GST resulted in an unforeseen tax liability that was not contemplated at the time of entering into agreements, leading to a financial burden. They sought reimbursement of this differential tax amount and challenged the relevant clause of the Finance Department Memorandum as arbitrary. Revenue's Contention: The Revenue submitted revised guidelines issued on December 10, 2018, which provided a detailed procedure for calculating the GST-inclusive work value for balance work on contracts tendered before July 1, 2017. This indicated the State's acknowledgment of the issue and its attempt to provide a mechanism for resolution.

Sections Cited

Not specified in the judgment

AI-generated summary — verify with the full judgment below

02.

12.02.2019

By way of this writ petition, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to declare Clause 6 of the Finance Department Memorandum dated 22.07.2017 as arbitrary, unfair and unreasonable.

Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST issued by

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.