Nirakara Samal vs. State Of Odisha
Held
The Court noted that the State Government had issued revised guidelines on December 10, 2018, to address the difficulties faced by contractors due to the GST regime for works contracts. These guidelines provided a detailed procedure for determining the GST-inclusive work value for the balance work executed after July 1, 2017, for tenders invited before that date. The procedure involved ascertaining the work done after June 30, 2017, determining its revised estimated work value as per the Revised SoR-2014, adjusting it for tender premium/discount, and then adding the applicable GST. The guidelines stipulated that if the revised GST-inclusive work value for the balance work exceeded the original agreement value for that portion, the contractor would be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority was directed to consider and dispose of the representation in light of the revised guidelines dated December 10, 2018, expeditiously, preferably by April 30, 2019. No coercive action was to be taken against the petitioner until April 30, 2019. The writ petition was disposed of with liberty to the petitioner to challenge the authority's decision if aggrieved.
Facts
The petitioner, a works contractor, filed a writ petition challenging the action of the opposite parties (State authorities) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that they were required to pay GST on works contracts entered into before the GST regime, which was not originally envisaged. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines provided a procedure for determining the GST-inclusive work value for balance work executed after July 1, 2017, on tenders invited before that date based on the Schedule of Rates – 2014 (SoR-2014).
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly thereafter? Petitioner's contention: The petitioner argued that the introduction of GST resulted in an additional tax burden not contemplated at the time of entering into the agreements, and therefore, they should be reimbursed for this differential tax amount. Revenue's contention: The Additional Government Advocate submitted that revised guidelines were issued by the Government of Odisha, Finance Department, on December 10, 2018, which provided a mechanism for addressing the claims of contractors for additional GST amounts on works executed post-GST, based on tenders invited pre-GST. The State relied on these revised guidelines.
Sections Cited
Section 73, Section 129, Rule 86A
AI-generated summary — verify with the full judgment below
20.02.2019
Heard learned counsel for the parties.
By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN-C
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.