Nirakar Samal vs. State Of Odisha
Held
The Court noted that the State Government had issued revised guidelines on 10.12.2018 to address the issues faced by contractors due to the transition to GST for works contracts. These guidelines provide a detailed procedure for determining the GST-inclusive work value for balance work executed after 30.06.2017, considering the original agreement, revised Schedule of Rates (SoR-2014), and tender premium/discount. The guidelines stipulate that if the revised GST-inclusive work value for the balance work is more than the original agreement work value, the contractor is to be reimbursed for the excess amount. Conversely, if it is less, the payment is to be reduced, and any excess payment already made is to be recovered. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated 10.12.2018, preferably by 30.04.2019. The Court also stated that if the petitioner is aggrieved by the authority's decision, they can challenge it. No coercive action is to be taken against the petitioner until 30.04.2019. The writ petition was disposed of with these directions.
Facts
The petitioner, a works contractor, filed a writ petition challenging the opposite parties' action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) on 01.07.2017. The petitioner's grievance was that they were required to pay GST on works contracts entered into before the GST regime, which was not anticipated in the original agreements. The State submitted revised guidelines issued by the Finance Department, Government of Odisha, on 10.12.2018, superseding earlier guidelines from 07.12.2017, to address such issues. These revised guidelines provide a procedure for determining the GST-inclusive work value for balance work executed after 01.07.2017, based on revised Schedule of Rates (SoR-2014) and original agreement terms, including tender premium/discount.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to 01.07.2017 but executed partly or wholly thereafter, considering the provisions of the GST regime and the nature of works contracts as composite supply. Petitioner's contention: The petitioner argued that the introduction of GST resulted in an unforeseen tax liability on works contracts that were agreed upon under the previous tax regime, leading to a financial burden not contemplated in the original agreements. They sought reimbursement of this differential tax amount. Revenue's contention: The State submitted revised guidelines issued by the Finance Department on 10.12.2018, which provide a mechanism for calculating the GST-inclusive work value for balance work executed after the GST implementation. These guidelines aim to address the claims of contractors for additional amounts towards GST on works tendered before 01.07.2017 but executed thereafter.
AI-generated summary — verify with the full judgment below
20.02.2019
Heard learned counsel for the parties.
By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN-C
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.