Nirakar Samal vs. State Of Odisha
Held
The Court acknowledged the issue faced by contractors due to the transition to GST for works contracts tendered before July 1, 2017, but executed thereafter. The Court noted the submission of revised guidelines by the Revenue dated December 10, 2018, which provided a mechanism for addressing such claims. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, detailing their grievance. The authority was then directed to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by April 30, 2019. The Court also stated that if the petitioner remained aggrieved by the authority's decision, they would be at liberty to challenge it. No coercive action was to be taken against the petitioner until April 30, 2019. The Court did not expressly leave any issue undecided, as the matter was disposed of with a direction for representation and consideration.
Facts
The petitioner, a works contractor, challenged the opposite parties' action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that they were required to pay GST on works contracts entered into before the GST regime, which was not initially envisaged in the agreements. The State submitted revised guidelines issued by the Finance Department of the Government of Odisha on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines provided a procedure for determining the GST-inclusive work value for balance work executed after July 1, 2017, where tenders were invited prior to that date.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly thereafter? Petitioner's contention: The petitioner argued that the introduction of GST resulted in an increased tax burden not contemplated at the time of entering into the agreements, and therefore, they should be reimbursed for this differential tax amount. Revenue's contention: The Revenue submitted revised guidelines issued by the Government of Odisha's Finance Department on December 10, 2018. These guidelines provided a detailed procedure for calculating the GST-inclusive work value for balance work executed after the GST implementation, where tenders were invited before July 1, 2017. The guidelines stipulated that if the revised GST-inclusive work value for the balance work exceeded the original agreement work value, the contractor would be reimbursed for the excess amount. Conversely, if it was less, the payment would be reduced, and any excess payment already made would be recovered.
Sections Cited
No specific sections of the CGST/SGST Act or Rules were explicitly discussed or relied upon in the judgment. The decision was based on the revised administrative guidelines issued by the Finance Department of the Government of Odisha.
AI-generated summary — verify with the full judgment below
20.02.2019
Heard learned counsel for the parties.
By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN-C
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.