AI SummaryRemanded

Held

The Court acknowledged the revised guidelines issued by the Government of Odisha's Finance Department on December 10, 2018, which provide a framework for addressing the claims of works contractors for differential GST amounts on contracts entered into before July 1, 2017, but executed thereafter. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within four weeks, detailing their grievance. The authority is then mandated to consider and dispose of this representation in light of the aforementioned revised guidelines, preferably by May 31, 2019. The Court also stated that if the petitioner is aggrieved by the authority's decision, they are at liberty to challenge it. No coercive action is to be taken against the petitioner until May 31, 2019. The writ petition was disposed of with these directions.

Facts

The petitioner, a works contractor, filed a writ petition challenging the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that they were required to pay GST on contracts entered into before the GST regime, which was not originally envisaged. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines addressed the issue of works contracts tendered before July 1, 2017, but executed partly or wholly after that date, outlining a procedure for calculating the differential GST amount payable to contractors.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts tendered before July 1, 2017, but executed partly or wholly after that date? Petitioner's contention: The petitioner argued that they are facing difficulties due to the introduction of GST, as they are required to pay tax that was not contemplated when the agreements were entered into. They seek reimbursement for this additional tax burden. Revenue/State's contention: The State submitted revised guidelines issued by the Finance Department on December 10, 2018. These guidelines provide a specific procedure for determining the amount payable to works contractors in cases where tenders were invited before July 1, 2017, but payments for the balance work were made after the implementation of GST. The guidelines aim to address the differential tax amount by calculating the revised GST-inclusive work value for the balance work.

AI-generated summary — verify with the full judgment below

02.

27.02.2019

Heard learned counsel for the parties.

By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN-CT

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.