P.D Infrastructure vs. Executive Engineer
Held
The Court acknowledged the issue concerning works contracts entered into before July 1, 2017, but executed after the implementation of GST. The State had issued revised guidelines on December 10, 2018, to address this specific situation. The Court directed the petitioner to make a comprehensive representation before the appropriate authority, ventilating their grievance within four weeks. The authority was then directed to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by May 31, 2019. The Court also stated that if the petitioner remained aggrieved by the authority's decision, they would be at liberty to challenge it. No coercive action was to be taken against the petitioner until May 31, 2019. The Court did not decide the ultimate entitlement to reimbursement but provided a procedural mechanism for its determination.
Facts
The petitioner, a works contractor, challenged the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that they were required to pay GST on contracts entered into before the GST regime, which was not initially envisaged. The State submitted revised guidelines issued by the Government of Odisha, Finance Department, on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines addressed the issue of works contracts tendered before July 1, 2017, but executed partly or wholly after that date, outlining a procedure for determining the payable amount to works contractors.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount due to the change in the tax regime from VAT to GST for works contracts tendered before July 1, 2017, but executed after that date? Petitioner's contention: The petitioner argued that the introduction of GST resulted in an additional tax burden that was not contemplated when the agreements were entered into, and therefore, they should be reimbursed for this differential tax amount. They relied on the principle that tax liabilities should not be imposed retrospectively or in a manner that was not agreed upon at the time of contract execution. Revenue/State's contention: The State submitted revised guidelines issued by the Finance Department on December 10, 2018. These guidelines provided a specific procedure for calculating the GST-inclusive work value for the balance work executed after July 1, 2017, and stipulated that the contractor would be reimbursed for any excess amount if the revised GST-inclusive work value exceeded the original agreement work value for the balance work. The State relied on these revised guidelines as the basis for resolving such disputes.
Sections Cited
Not specified in the judgment
AI-generated summary — verify with the full judgment below
27.02.2019
Heard learned counsel for the parties.
By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN-CT
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.