Assa Project And Engineering PVT.LTD. vs. State Of Odisha

WP(C)/5786/2019HC OrissaGSTCNR ODHC01015119201913 March 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA5 pages
AI SummaryRemanded

Held

The Court acknowledged the petitioner's grievance regarding the differential tax amount due to the transition to GST. The State presented revised guidelines dated December 10, 2018, which provide a detailed procedure for determining the GST-inclusive work value for the balance portion of works contracts that were tendered before July 1, 2017, but executed thereafter. These guidelines outline how to ascertain the balance work's value based on the revised Schedule of Rates (SoR-2014), apply tender premium/discount, and add the applicable GST rate. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within one week, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by March 31, 2019. The Court also stated that if the petitioner is aggrieved by the authority's decision, they are at liberty to challenge it. No coercive action is to be taken against the petitioner until March 31, 2019. The issue of reimbursement itself was not definitively decided but was to be processed under the new guidelines.

Facts

The petitioner, a works contractor, challenged the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that they were required to pay GST on contracts entered into before the GST regime, which was not originally envisaged. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines address how to handle works contracts tendered before July 1, 2017, but executed partly or wholly after that date, by providing a procedure to determine the GST-inclusive work value for the balance work.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into before July 1, 2017, but executed thereafter? Petitioner's contention: The petitioner argued that the introduction of GST necessitated paying tax that was not contemplated at the time of entering into the agreement, thus causing a financial burden. They sought reimbursement of this differential tax amount. Revenue/State's contention: The State submitted revised guidelines dated December 10, 2018, which provide a framework for calculating the GST-inclusive work value for the balance work on contracts tendered before July 1, 2017. These guidelines aim to address the claims of contractors for additional amounts towards GST. The State relied on the Office Memorandum No. FIN-CTI-TAX-0045-2017/38535/F dated 10.12.2018.

AI-generated summary — verify with the full judgment below

02.

13.03.2019

Heard Mr. S.K. Dalai, learned counsel for the petitioner and learned Additional Government Advocate for the State- opposite parties.

By way of this writ petition, in substance, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST is

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.