Gajendra Prasad Panda vs. State Of Orissa
Held
The Court noted that the State had issued revised guidelines on December 10, 2018, to address the grievances of works contractors regarding the GST transition. These guidelines provide a detailed procedure for determining the GST-inclusive work value for the balance work of contracts tendered before July 1, 2017, but executed thereafter. The procedure involves ascertaining the work done after June 30, 2017, determining its revised estimated work value as per the Revised SoR-2014, adjusting it by the tender premium/discount, and then adding the applicable GST rate. The guidelines also stipulate that if the revised GST-inclusive work value for the balance work is more than the original agreement work value, the contractor is to be reimbursed for the excess amount. Conversely, if it is less, the payment is to be reduced, and any excess payment already made is to be recovered. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, which the authority would consider and dispose of in light of the revised guidelines dated December 10, 2018, preferably by April 30, 2019. The Court also granted a stay on coercive action against the petitioner until April 30, 2019.
Facts
The petitioner, a works contractor, challenged the action of the opposite parties (State authorities) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner argued that they were required to pay GST on contracts entered into before the GST regime, which was not envisaged at the time of agreement. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines address how to handle works contracts tendered before July 1, 2017, but executed partly or wholly after that date, outlining a procedure for determining the GST-inclusive work value for the balance work and reimbursement or recovery of amounts.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into before July 1, 2017, but executed partly or wholly after that date. Petitioner's contention: The petitioner argued that the introduction of GST resulted in an additional tax burden not contemplated in the original agreements, and therefore, they should be reimbursed for this differential tax amount. They sought to quash Clause 6 of the Finance Department Memorandum dated July 22, 2017, which likely addressed the issue in a manner unfavorable to contractors. Revenue's contention: The State submitted revised guidelines issued on December 10, 2018, which provide a mechanism for calculating the GST-inclusive work value for the balance work and for reimbursing contractors if the revised value exceeds the original agreement value, or recovering excess payments if it is less. The State implicitly argued that these revised guidelines offer a procedural remedy.
Sections Cited
CGST Act, SGST Act
AI-generated summary — verify with the full judgment below
20.03.2019
Heard learned counsel for the parties.
By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 6 of the Finance Department Memorandum dated 22.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guidelines relating to works contract under
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.