Gajendra Prasad Panda vs. State Of Orissa
Held
The Court did not directly decide the entitlement to reimbursement but rather directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks. This representation should ventilate the petitioner's grievance in light of the revised guidelines issued by the Finance Department of the Government of Odisha on December 10, 2018. The authority is mandated to consider and dispose of this representation as expeditiously as possible, preferably by April 30, 2019. The Court also stated that if the petitioner is aggrieved by the decision of the authority, they are at liberty to challenge it. No coercive action is to be taken against the petitioner until April 30, 2019. The Court did not expressly leave any issue undecided, but the core issue of reimbursement was deferred for determination by the administrative authority.
Facts
The petitioner, a works contractor, challenged the action of the opposite parties (State authorities) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner argued that they were required to pay GST on contracts entered into before the GST regime, which was not envisaged at the time of agreement. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines provided a procedure for determining the GST-inclusive work value for balance work executed after July 1, 2017, on contracts tendered before that date. The Court directed the petitioner to make a representation to the appropriate authority based on these revised guidelines.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly after that date? Petitioner's contention: The petitioner argued that the introduction of GST imposed a tax liability that was not contemplated when the agreements were entered into, and therefore, they should be reimbursed for this additional tax burden. They sought to quash Clause 6 of the Finance Department Memorandum dated July 22, 2017, which likely addressed the issue of tax reimbursement. Revenue's contention: The State submitted revised guidelines dated December 10, 2018, which provided a mechanism for calculating the GST-inclusive work value for balance work executed after the GST implementation. The State indicated that these guidelines superseded previous ones and offered a way to address the contractors' grievances. The State relied on the Office Memorandum No. FIN-CTI-TAX-0045-2017/38535/F dated 10.12.2018.
Sections Cited
None explicitly mentioned as being discussed or interpreted in the judgment, but the context relates to the transition to GST and works contracts.
AI-generated summary — verify with the full judgment below
20.03.2019
Heard learned counsel for the parties.
By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 6 of the Finance Department Memorandum dated 22.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guidelines relating to works contract under
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.