Sanyasi Behera vs. State Of Odisha
Held
The Court noted that the State Government had issued revised guidelines on December 10, 2018, to address the difficulties faced by works contractors due to the GST regime. These guidelines provided a detailed procedure for determining the GST-inclusive work value for balance work on contracts entered into before July 1, 2017, and executed thereafter. The guidelines stipulated that if the revised GST-inclusive work value for the balance work exceeded the original agreement work value for that balance work, the works contractor would be reimbursed for the excess amount. Conversely, if it was less, the payment would be reduced, and any excess payment already made would be recovered. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority was directed to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by June 29, 2019. The Court also stated that if the petitioner was aggrieved by the authority's decision, they could challenge it. No coercive action was to be taken against the petitioner until June 29, 2019. The issue of quashing Clause 6 of the Finance Department Memorandum dated July 22, 2017, was implicitly addressed by the direction to follow the revised guidelines.
Facts
The petitioner, a works contractor, filed a writ petition challenging the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner argued that they were required to pay GST on contracts entered into before the GST regime, which was not originally envisaged. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines dated July 22, 2017, and December 7, 2017. These revised guidelines provided a procedure for determining the GST-inclusive work value for balance work on contracts tendered before July 1, 2017, but executed partly or wholly after that date, allowing for reimbursement of excess amounts.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed thereafter? (Question of law) 2. Whether Clause 6 of the Finance Department Memorandum dated July 22, 2017, is liable to be quashed? Petitioner's contention: The petitioner argued that the introduction of GST necessitated payment of taxes not contemplated in the original agreements, leading to a financial burden. They sought reimbursement of this differential tax amount. Revenue's contention: The learned Additional Government Advocate submitted that the Government had issued revised guidelines on December 10, 2018, which addressed the issue of works contracts under GST. These guidelines provided a mechanism for calculating and potentially reimbursing the differential tax amount for balance work executed after the GST implementation.
Sections Cited
Section 73, Section 129, Rule 86A
AI-generated summary — verify with the full judgment below
17.04.2019
Heard learned counsel for the parties.
By way of this writ petition, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 6 of the Finance Department Memorandum dated 22.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guidelines relating to works contr
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.