Bipin Bihari Behera vs. The Principal Secretary Finance Department
Held
The Court acknowledged the revised guidelines issued by the Government of Odisha, Finance Department, on December 10, 2018, which provided a framework for addressing the differential tax amounts for works contracts executed post-GST implementation. The guidelines outline a procedure to ascertain the balance work done after June 30, 2017, determine its revised estimated work value as per the Revised Schedule of Rates (SoR-2014) and tender premium/discount, and then add the applicable GST rate. Crucially, the guidelines stipulate that if this revised GST-inclusive work value for the balance work is more than the original agreement work value for the balance work, the works contractor is to be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by September 30, 2019. The Court also stated that if the petitioner is aggrieved by the authority's decision, they can challenge it. No coercive action was to be taken against the petitioner until September 30, 2019. The issue of whether the petitioner was *entitled* to reimbursement was not directly decided but was to be processed under the revised guidelines.
Facts
The petitioner filed a writ petition challenging the action of the opposite parties in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that the introduction of GST necessitated paying taxes not originally envisaged in the agreements. The Government of Odisha, Finance Department, issued revised guidelines on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines addressed the difficulties faced by contractors regarding works contracts under GST, particularly for tenders invited before July 1, 2017, but executed partly or wholly after that date. The court noted that no parties appeared for the hearing.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount due to the change in tax regime from VAT to GST for works contracts entered into before July 1, 2017, but executed thereafter? The petitioner argued that the introduction of GST resulted in an additional tax burden that was not contemplated at the time of entering into the agreements, leading to a financial disadvantage. The petitioner sought reimbursement for this differential tax amount. The revenue/State, through the Additional Government Advocate, presented revised guidelines issued by the Government of Odisha, Finance Department, on December 10, 2018. These guidelines provided a procedure for determining the GST-inclusive work value for the balance work executed after the GST implementation, allowing for reimbursement if the revised value exceeded the original agreement value. The State's contention was that these revised guidelines offered a mechanism to address the petitioner's grievance.
Sections Cited
None explicitly discussed or named in the judgment text provided.
AI-generated summary — verify with the full judgment below
26.06.2019
None appears for the parties.
By way of this writ petition, the petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
The Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. Learned Addl. Government Advocate has filed an Additional Counter Affidavit of O.P.-authority in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN- CTI-TAX-00
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.