Nilachala Sahu vs. E.E.,Rural Work

WP(C)/20864/2018HC OrissaGSTCNR ODHC01060803201826 June 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court did not decide the core issue of entitlement to reimbursement directly but disposed of the writ petition by directing the petitioner to make a comprehensive representation before the appropriate authority within four weeks. The Court mandated that the authority must consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, issued by the Finance Department, Government of Odisha, as expeditiously as possible, preferably by September 30, 2019. The Court also stated that if the petitioner remained aggrieved by the authority's decision, they would be at liberty to challenge it. Furthermore, no coercive action was to be taken against the petitioner until September 30, 2019. The Court expressly left undecided the ultimate outcome of the petitioner's claim pending the authority's decision.

Facts

The petitioner filed a writ petition challenging the action of the opposite parties in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that they were required to pay GST on works contracts, a tax not anticipated when agreements were entered into under the previous VAT regime. The Government of Odisha, Finance Department, issued revised guidelines on December 10, 2018, superseding earlier guidelines from December 7, 2017, to address difficulties faced by contractors regarding works contracts under GST. These revised guidelines provided a procedure for determining the GST-inclusive work value for balance work executed after July 1, 2017, where tenders were invited prior to that date.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount due to the change in tax regime from VAT to GST for works contracts executed partly or wholly after July 1, 2017, where tenders were invited prior to this date? Petitioner's Contention: The petitioner argued that the introduction of GST resulted in an unforeseen tax liability on works contracts, as the original agreements were based on the VAT regime. They sought reimbursement for this differential tax amount. Revenue/State's Contention: The State, through the Additional Government Advocate, filed an affidavit annexing revised guidelines issued by the Finance Department. These guidelines, dated December 10, 2018, provided a framework for calculating the GST-inclusive work value for balance work and stipulated that contractors would be reimbursed if the revised GST-inclusive work value exceeded the original agreement value for the balance work. The State relied on these revised guidelines to address the issue.

Sections Cited

CGST/SGST Act

AI-generated summary — verify with the full judgment below

02.

26.06.2019

None appears for the parties.

By way of this writ petition, the petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

The Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. Learned Addl. Government Advocate has filed an Additional Counter Affidavit of O.P.-authority in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN- CTI-TAX-00

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.