Held

The Court noted that the Government of Odisha had issued revised guidelines on December 10, 2018, to address the issue of differential tax amounts for works contracts executed under the GST regime. These guidelines provided a detailed procedure for determining the GST-inclusive work value for the balance work performed after June 30, 2017, for tenders invited before July 1, 2017. The procedure involves ascertaining the quantity and value of work done after June 30, 2017, determining the revised estimated work value as per revised Schedule of Rates (SoR-2014), adjusting for tender premium/discount, and adding the applicable GST rate. The guidelines stipulate that if the revised GST-inclusive work value is more than the original agreement value for the balance work, the contractor is to be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, which the authority would consider and dispose of in light of the revised guidelines by September 30, 2019. The Court also stated that if the petitioner is aggrieved by the authority's decision, they can challenge it further. No coercive action was to be taken against the petitioner until September 30, 2019.

Facts

The petitioner filed a writ petition challenging the action of the opposite parties in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that they were required to pay GST on works contracts, a tax not anticipated when agreements were entered into under the previous VAT regime. The Government of Odisha, Finance Department, issued revised guidelines on December 10, 2018, superseding earlier guidelines from December 7, 2017, to address difficulties faced by contractors regarding works contracts under GST. These revised guidelines provided a procedure for calculating the GST-inclusive work value for balance work executed after July 1, 2017, on tenders invited before that date.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts executed partly or wholly after July 1, 2017, where tenders were invited prior to this date? 2. Whether the revised guidelines issued by the Government of Odisha on December 10, 2018, provide an adequate mechanism for determining the amount payable to works contractors in such cases? Petitioner's contention: The petitioner argued that they are facing difficulties due to the introduction of GST, as they are required to pay taxes that were not envisaged at the time of entering into the agreements. They sought reimbursement of the differential tax amount. Revenue's contention: The Additional Government Advocate filed an Additional Counter Affidavit annexing the revised guidelines dated December 10, 2018, which provided a procedure for calculating the GST-inclusive work value for balance work. The revenue implicitly argued that these guidelines addressed the petitioner's grievance and provided a framework for resolution.

AI-generated summary — verify with the full judgment below

02.

26.06.2019

None appears for the parties.

By way of this writ petition, the petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

The Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. Learned Addl. Government Advocate has filed an Additional Counter Affidavit of O.P.-authority in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN- CTI-TAX-00

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.