Held

The Court noted that the Government of Odisha had issued revised guidelines on December 10, 2018, to address the issue of differential tax amounts for works contracts executed after the GST implementation but tendered before it. These guidelines provide a detailed procedure for calculating the revised GST-inclusive work value for the balance work. If this revised value is higher than the original agreement value for the balance work, the contractor is to be reimbursed for the excess amount. Conversely, if it is lower, the payment is to be reduced, and any excess payment already made is to be recovered. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, preferably by September 30, 2019. The Court also stated that if the petitioner is aggrieved by the authority's decision, they can challenge it. No coercive action was to be taken against the petitioner until September 30, 2019. The writ petition was disposed of with these directions.

Facts

The petitioner filed a writ petition challenging the action of the opposite parties (revenue/State) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that the GST liability was not envisaged when the agreement was entered into. The Government of Odisha, Finance Department, issued revised guidelines on December 10, 2018, superseding earlier guidelines from December 7, 2017, to address difficulties faced by works contractors. These revised guidelines provide a procedure for determining the amount payable to contractors for works tendered before July 1, 2017, but executed partly or wholly after that date.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount due to the change in tax regime from VAT to GST for works contracts tendered before July 1, 2017, but executed after that date? Petitioner's contention: The petitioner argued that the introduction of GST resulted in an additional tax burden that was not anticipated at the time of entering into the agreement, and therefore, they should be reimbursed for this differential tax amount. The petitioner's grievance stems from the change in tax structure impacting works contracts. Revenue/State's contention: The revenue/State, through an Additional Counter Affidavit, presented revised guidelines issued by the Government of Odisha, Finance Department, on December 10, 2018. These guidelines outline a specific procedure for calculating the GST-inclusive work value for the balance work and determining the amount payable to the works contractor, including provisions for reimbursement or recovery of excess payments.

Sections Cited

Not specified in the judgment

AI-generated summary — verify with the full judgment below

02.

28.06.2019

None appears for the parties.

By way of this writ petition, the petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

The Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. Learned Addl. Government Advocate has filed an Additional Counter Affidavit of O.P.-authority in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN- CTI-TAX-00

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.