Msp Infracon PVT.LTD. vs. The Executive Engineer, Ganjam (R And B )Division

WP(C)/10680/2019HC OrissaGSTCNR ODHC01032386201928 June 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE S.K.MISHRA4 pages
AI SummaryRemanded

Held

The Court acknowledged the issue faced by contractors due to the transition from VAT to GST, particularly for works contracts tendered before July 1, 2017, but executed thereafter. The Court noted that the Government of Odisha, Finance Department, had issued revised guidelines on December 10, 2018, to address these concerns. These guidelines established a procedure for determining the GST-inclusive work value for the balance work, including ascertaining the work value as per the original agreement, determining the revised estimated work value as per the revised Schedule of Rates (SoR-2014), adjusting for tender premium/discount, and adding the applicable GST rate. Crucially, the guidelines stipulated that if the revised GST-inclusive work value for the balance work exceeded the original agreement work value for that balance work, the works contractor was to be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority was directed to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by September 30, 2019. The Court also granted liberty to the petitioner to challenge the authority's decision if aggrieved and ordered that no coercive action would be taken against the petitioner until September 30, 2019.

Facts

The petitioner, a works contractor, challenged the action of the opposite parties (revenue/State) for not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that they were required to pay GST on works contracts entered into before the GST regime, which was not initially envisaged. The State Government, through the Finance Department, issued revised guidelines on December 10, 2018, superseding earlier guidelines from December 7, 2017, to address difficulties faced by contractors regarding works contracts under GST. These revised guidelines provided a procedure for calculating and reimbursing the differential tax amount for balance work executed after July 1, 2017, based on tenders invited before that date.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts executed partly or wholly after July 1, 2017, where tenders were invited prior to this date? Petitioner's contention: The petitioner argued that they are facing difficulties due to the introduction of GST, as they are required to pay tax on works contracts that were not contemplated at the time of entering into the agreement. They sought reimbursement of the additional tax burden incurred due to the GST regime on the balance work executed post-July 1, 2017. Revenue/State's contention: The State Government, through the Additional Government Advocate, filed an Additional Counter Affidavit annexing revised guidelines issued by the Finance Department on December 10, 2018. These guidelines provided a framework for dealing with claims for additional amounts towards GST for works put to tender before July 1, 2017, but executed thereafter. The State relied on these revised guidelines to address the petitioner's grievance.

AI-generated summary — verify with the full judgment below

02.

28.06.2019

None appears for the parties.

By way of this writ petition, the petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

The Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. Learned Addl. Government Advocate has filed an Additional Counter Affidavit of O.P.-authority in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN- CTI-TAX-00

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.