Msp Infracon PVT.LTD. vs. The Executive Engineer,Paralakhemundi(R And B) Division
Held
The Court noted that the State Government had issued revised guidelines on December 10, 2018, to address the issue of differential tax amounts for works contracts executed after the introduction of GST, for tenders invited prior to July 1, 2017. These guidelines provided a mechanism for calculating the revised GST-inclusive work value for the balance work. If this revised value was higher than the original agreement value for the balance work, the contractor was to be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority was instructed to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by September 30, 2019. The Court also stated that if the petitioner was aggrieved by the authority's decision, they could challenge it. No coercive action was to be taken against the petitioner until September 30, 2019. The writ petition was disposed of with these directions.
Facts
The petitioner, a works contractor, challenged the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that they were required to pay GST on contracts entered into before the GST regime, which was not initially envisaged. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines addressed the difficulties faced by contractors regarding works contracts under GST, particularly for tenders invited before July 1, 2017, but executed partly or wholly after that date.
Key Issues
1. Whether the petitioner is entitled to reimbursement for the differential tax amount due to the change in tax regime from VAT to GST for works contracts entered into before July 1, 2017, but executed thereafter? Petitioner's Contention: The petitioner argued that the introduction of GST necessitated payment of tax that was not contemplated when the agreements were made, leading to a financial burden. They sought reimbursement for this differential tax amount. Revenue's Contention: The State, through the Additional Government Advocate, submitted revised guidelines issued by the Government of Odisha, Finance Department, on December 10, 2018. These guidelines provided a procedure for determining the amount payable to works contractors in cases where tenders were invited before July 1, 2017, but payments for balance work were made after the implementation of GST. The guidelines outlined how to ascertain the balance work, determine its revised estimated value as per the revised Schedule of Rates (SoR-2014), apply tender premium/discount, and add the applicable GST rate to arrive at a GST-inclusive work value. The guidelines also stipulated that if the revised GST-inclusive work value exceeded the original agreement work value for the balance work, the contractor would be reimbursed for the excess amount.
AI-generated summary — verify with the full judgment below
28.06.2019
None appears for the parties.
By way of this writ petition, the petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
The Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. Learned Addl. Government Advocate has filed an Additional Counter Affidavit of O.P.-authority in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN- CTI-TAX-00
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.