Debi Prasad Samantaray vs. Principal Secretary Finance Deptt.

WP(C)/8572/2019HC OrissaGSTCNR ODHC01024341201903 July 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court acknowledged that the issue of differential tax amounts for works contracts due to the GST transition was a recurring one. The State Government had issued revised guidelines on December 10, 2018, to address the grievances of contractors who had entered into agreements before July 1, 2017, but whose works were executed partly or wholly after the GST implementation. These guidelines provided a detailed procedure for determining the GST-inclusive work value for the balance work, including provisions for reimbursement if the revised GST-inclusive value exceeded the original agreement value. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within four weeks, ventilating their grievance. The authority was instructed to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by September 30, 2019. The Court also stated that if the petitioner remained aggrieved by the authority's decision, they would be at liberty to challenge it. No coercive action was to be taken against the petitioner until September 30, 2019.

Facts

The petitioner, a works contractor, challenged the opposite parties' action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that they were required to pay GST on contracts entered into before the GST regime, which was not initially envisaged. The State Government, in response to similar issues faced by contractors, issued revised guidelines on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines provided a procedure for calculating the GST-inclusive work value for balance work executed after the GST implementation, allowing for reimbursement of excess amounts paid by contractors.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount due to the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly after that date? Petitioner's contention: The petitioner argued that the introduction of GST resulted in an additional tax burden not contemplated at the time of entering into the agreements, necessitating reimbursement of the differential tax amount. Revenue/State's contention: The State Government, through the Additional Government Advocate, placed on record revised guidelines issued on December 10, 2018, which provided a mechanism for calculating and reimbursing the differential GST amount for works contracts executed after the GST implementation but tendered before it. The State relied on these revised guidelines to address the grievance.

AI-generated summary — verify with the full judgment below

02.

03.07.2019

None appears for the parties.

2.

By way of this writ petition, the petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. 3. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

4.

The Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. Learned Addl. Government Advocate has filed an Additional Counter Affidavit of O.P.-authority in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN- CTI-

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.