M/S.Umsl LTD. vs. State Of Odisha,Works Dept.

WP(C)/11178/2019HC OrissaGSTCNR ODHC01034128201917 July 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court noted that the State Government had issued revised guidelines on December 10, 2018, to address the issue of works contracts executed after the implementation of GST for tenders invited prior to July 1, 2017. These guidelines provide a detailed procedure for determining the GST-inclusive work value for the balance work. Specifically, point 3(vii) of the revised guidelines states that if the revised GST-inclusive work value for the balance work is more than the original agreement work value for the balance work, the works contractor is to be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by September 30, 2019. The Court also stated that if the petitioner is aggrieved by the authority's decision, they are free to challenge it. No coercive action is to be taken against the petitioner until September 30, 2019.

Facts

The petitioner, a works contractor, filed a writ petition challenging the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that they were required to pay GST on works contracts entered into before the GST regime, which was not initially envisaged in the agreements. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines provided a procedure for determining the GST-inclusive work value for balance work executed after the GST implementation, where tenders were invited before July 1, 2017.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly thereafter? The petitioner argued that the introduction of GST resulted in an additional tax burden not contemplated at the time of entering into the agreements, leading to a claim for reimbursement of this differential tax amount. The revenue, represented by the State, submitted revised guidelines issued by the Finance Department. These guidelines, dated December 10, 2018, provided a mechanism for calculating the GST-inclusive work value for balance work executed after July 1, 2017, for contracts tendered before that date. The guidelines stipulated that if the revised GST-inclusive work value for the balance work exceeded the original agreement work value for that balance work, the contractor would be reimbursed for the excess amount. The revenue relied on these revised guidelines as the basis for addressing the petitioner's grievance.

AI-generated summary — verify with the full judgment below

02.

17.07.2019

Heard learned counsel for the parties.

By way of this writ petition, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.