M/S. Abs Engineering And Developers vs. State Of Odisha,Water Resources Dept.
Held
The Court acknowledged the petitioner's grievance regarding the differential tax amount due to the GST regime change. The Revenue presented revised guidelines dated December 10, 2018, which provide a mechanism for calculating the GST-inclusive work value for balance work executed after June 30, 2017, for contracts tendered before July 1, 2017. These guidelines stipulate that if the revised GST-inclusive work value for the balance work is higher than the original agreement work value for that balance work, the works contractor is to be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by September 30, 2019. The Court also stated that if the petitioner is aggrieved by the authority's decision, they are free to challenge it. No coercive action is to be taken against the petitioner until September 30, 2019. The issue of reimbursement was not directly decided but was remitted for consideration under the revised guidelines.
Facts
The petitioner, a works contractor, filed a writ petition challenging the action of the opposite parties (State) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective from July 1, 2017. The petitioner's grievance was that the introduction of GST necessitated paying tax on works contracts that was not anticipated when the agreements were entered into. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017, to address issues related to works contracts under GST for tenders invited before July 1, 2017, but executed partly or wholly after that date.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts executed partly or wholly after July 1, 2017, when tenders were invited prior to that date. Petitioner's contention: The petitioner argued that the introduction of GST resulted in an additional tax burden that was not envisaged at the time of entering into the agreements, and therefore, they should be reimbursed for this differential tax amount. The petitioner's grievance stems from the fact that the original contract rates were inclusive of pre-GST taxes, and the new GST regime imposes a tax that was not accounted for in the original pricing. Revenue's contention: The Revenue submitted revised guidelines issued by the Government of Odisha, Finance Department, on December 10, 2018. These guidelines provide a procedure for determining the GST-inclusive work value for the balance work executed after the GST implementation, and stipulate reimbursement if the revised value exceeds the original agreement value, or recovery if it is less. The Revenue relied on these revised guidelines to address the petitioner's claim.
AI-generated summary — verify with the full judgment below
24.07.2019
Heard learned counsel for the parties.
By way of this writ petition, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.