M/S Tilak Chand Agrawal Partnership Firm vs. State Of Odisha

WP(C)/13357/2019HC OrissaGSTCNR ODHC01040809201902 August 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court noted that the State Government had issued revised guidelines on December 10, 2018, to address the issues faced by contractors due to the implementation of GST on works contracts. These guidelines provide a detailed procedure for calculating the GST-inclusive work value for the balance work executed after June 30, 2017, when tenders were invited before July 1, 2017. The guidelines stipulate that if the revised GST-inclusive work value for the balance work is more than the original agreement work value, the works contractor is to be reimbursed for the excess amount. Conversely, if it is less, the payment is to be reduced, and any excess payment already made is to be recovered. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, expeditiously, preferably by September 30, 2019. The Court also granted a stay on coercive action against the petitioner until September 30, 2019.

Facts

The petitioner, a contractor, filed a writ petition challenging the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that they were required to pay GST on works contracts entered into before the GST regime, which was not originally envisaged. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines provided a procedure for determining the GST-inclusive work value for balance work executed after GST implementation, including provisions for reimbursement or recovery of excess payments.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts executed partly or wholly after July 1, 2017, when the tender was invited prior to that date? 2. Whether the revised guidelines issued by the Government of Odisha, Finance Department on December 10, 2018, provide an adequate mechanism for addressing the petitioner's grievance regarding the differential tax amount on works contracts? Petitioner's Contention: The petitioner argued that they are facing difficulties due to the change in tax regime and are required to pay GST on works contracts which was not anticipated when the agreements were entered into. They sought reimbursement of the additional tax burden. Revenue's Contention: The learned Additional Government Advocate submitted that the Government has issued revised guidelines on December 10, 2018, which address the issue of works contracts under GST and provide a procedure for determining the payable amount to contractors, including reimbursement for excess amounts.

AI-generated summary — verify with the full judgment below

02.

02.08.2019

Heard learned counsel for the parties.

By way of this writ petition, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.