Jeeban Chandra Sahu vs. The Principal Secretary Finance Dept.
Held
The Court noted that the State Government had issued revised guidelines on December 10, 2018, to address the issues faced by works contractors due to the transition from VAT to GST. These guidelines provide a mechanism for determining the GST-inclusive work value for the balance work executed after July 1, 2017, for contracts tendered before that date. Specifically, the guidelines outline a procedure to ascertain the work done after June 30, 2017, determine its revised estimated work value as per the Revised Schedule of Rates (SoR-2014), apply the tender premium/discount, and then add the applicable GST rate. If this revised GST-inclusive work value is more than the original agreement work value for the balance work, the contractor is to be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by October 31, 2019. The Court also stated that if the petitioner is aggrieved by the authority's decision, they are free to challenge it. No coercive action was to be taken against the petitioner until October 31, 2019.
Facts
The petitioner, a works contractor, filed a writ petition challenging the action of the opposite parties (State authorities) in not reimbursing the differential tax amount arising from the change in tax regime from Value Added Tax (VAT) to Goods and Services Tax (GST) effective from July 1, 2017. The petitioner's grievance was that they were required to pay GST on works contracts entered into before the GST regime, which was not envisaged in the original agreements. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017, to address issues related to works contracts under GST for tenders invited before July 1, 2017, but executed partly or wholly after that date.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed thereafter, under the provisions of the GST law and relevant government guidelines. Petitioner's contention: The petitioner argued that the introduction of GST resulted in an additional tax burden not contemplated in the original agreements, and therefore, they should be reimbursed for this differential tax amount. They relied on the principle that tax liabilities should not be unilaterally imposed on contractors for pre-existing contracts. Revenue/State's contention: The State submitted revised guidelines issued by the Finance Department on December 10, 2018, which provide a procedure for determining the GST-inclusive work value for the balance work executed after July 1, 2017. These guidelines allow for reimbursement of excess amounts if the revised GST-inclusive work value exceeds the original agreement value, or recovery if it is less. The State relied on these revised guidelines to address the petitioner's grievance.
AI-generated summary — verify with the full judgment below
21.08.2019
Heard learned counsel for the parties.
By way of this writ petition, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum N
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.