M/S.Abs Engineering And Developers vs. State Of Odisha
Held
The Court noted that the issue involved difficulties faced by contractors due to the change in the tax regime for works contracts under GST. The Government of Odisha, Finance Department, had issued revised guidelines on December 10, 2018, to address representations from contractors claiming additional amounts towards GST for works tendered before July 1, 2017, but executed after that date. These guidelines outlined a procedure for determining the GST-inclusive work value for the balance work, involving ascertaining the work done after June 30, 2017, determining its revised estimated work value as per the Revised Schedule of Rates – 2014 (SoR-2014), applying tender premium/discount, and then adding the applicable GST rate. The guidelines stipulated that if the revised GST-inclusive work value for the balance work exceeded the original agreement value, the contractor was to be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority was directed to consider and dispose of the representation in light of the revised guidelines dated December 10, 2018, expeditiously, preferably within three months. The Court also stated that if the petitioner was aggrieved by the authority's decision, they could challenge it. No coercive action was to be taken against the petitioner until January 6, 2020.
Facts
The petitioner, a works contractor, filed a writ petition challenging the action of the opposite parties (State/Revenue) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that they were required to pay GST on works contracts entered into before the GST regime, which was not anticipated in the original agreements. The State Government had issued revised guidelines on December 10, 2018, superseding earlier guidelines from December 7, 2017, to address difficulties faced by contractors regarding works contracts under GST. These revised guidelines provided a procedure for determining the GST-inclusive work value for balance work executed after GST implementation.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly thereafter? Petitioner's Contention: The petitioner argued that the introduction of GST resulted in an additional tax burden not envisaged in the original agreements, and they are entitled to reimbursement for this differential tax amount. Revenue's Contention: The judgment does not record any specific arguments made by the revenue or State. However, it notes that the issue involved difficulties faced by contractors due to the change in the regime regarding works contracts under GST and that the Government had issued revised guidelines to address these issues.
AI-generated summary — verify with the full judgment below
06.09.2019
None appears for the parties.
Since the issue involved in this case has already been decided by us earlier in number of cases, no purpose will be served by keeping the matter pending. Therefore, in the interest of justice, this writ petition is also disposed of in terms of the order passed earlier in similar matters.
By way of this writ petition, in substance, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
The Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department l
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.