M/S.Hindustan Builders vs. State Of Odisha

WP(C)/16155/2019HC OrissaGSTCNR ODHC01048725201918 September 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court noted that the State Government had issued revised guidelines on December 10, 2018, to address the issue of differential tax amounts for works contracts executed after the implementation of GST for tenders invited prior to July 1, 2017. These guidelines outline a procedure for calculating the revised GST-inclusive work value for the balance work. If this revised value is higher than the original agreement value for the balance work, the contractor is to be reimbursed for the excess amount. Conversely, if it is lower, the payment will be reduced, and any excess payment already made will be recovered. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by November 30, 2019. The petitioner retains the right to challenge the authority's decision if aggrieved. No coercive action is to be taken against the petitioner until November 30, 2019. The writ petition was disposed of accordingly.

Facts

The petitioner filed a writ petition challenging the opposite parties' action of not reimbursing the differential tax amount arising from the change in tax regime from Value Added Tax (VAT) to Goods and Services Tax (GST) effective from July 1, 2017. The petitioner's grievance was that the introduction of GST necessitated paying taxes not envisaged when the agreement was entered into. The State Government, through the Finance Department, issued revised guidelines on December 10, 2018, superseding earlier guidelines from December 7, 2017, to address difficulties faced by contractors regarding works contracts under GST for tenders invited before July 1, 2017, but executed partly or wholly after that date.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount due to the transition from VAT to GST for works contracts tendered before July 1, 2017, but executed after that date? The petitioner argued that the introduction of GST was not contemplated at the time of entering into the agreement, leading to an unforeseen tax burden. The State, through the Additional Government Advocate, presented revised guidelines issued by the Finance Department on December 10, 2018. These guidelines provide a procedure for determining the GST-inclusive work value for the balance work executed after GST implementation, allowing for reimbursement if the revised value exceeds the original agreement value, or recovery if it is less. The guidelines also address situations where rates for certain goods or services are not covered in the revised Schedule of Rates (SoR-2014).

AI-generated summary — verify with the full judgment below

02.

18.09.2019

None appears for the parties.

2.

By way of this writ petition, the petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. 3. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

4.

The Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. Learned Addl. Government Advocate has filed Additional Counter Affidavit of O.P.-authority in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN-CTI-TAX- 0045-

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.