Prabina Kumar Kuanr vs. State Of Odisha

WP(C)/16708/2019HC OrissaGSTCNR ODHC01050188201924 September 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court acknowledged the issue of contractors facing difficulties due to the change in tax regime from VAT to GST, particularly for works contracts tendered before July 1, 2017, but executed thereafter. The Court noted that the Government of Odisha had issued revised guidelines on December 10, 2018, to address these concerns. These guidelines outline a procedure to determine the GST-inclusive work value for the balance work by revising the Schedule of Rates (SoR) and applying the applicable GST rate. The guidelines also specify that if the revised GST-inclusive work value for the balance work is higher than the original agreement work value for that balance work, the contractor is to be reimbursed for the excess amount. Conversely, if it is lower, the payment is to be reduced, and any excess payment already made is to be recovered. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, which the authority was to consider and dispose of in light of the revised guidelines dated December 10, 2018, preferably by November 30, 2019. The Court also stated that no coercive action would be taken against the petitioner until November 30, 2019. The issue of whether the petitioner was *entitled* to reimbursement was not definitively decided but was remitted to the authority for consideration under the revised guidelines.

Facts

The petitioner filed a writ petition challenging the action of the opposite parties (revenue/State) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that the GST regime imposed taxes not originally envisaged when entering into works contract agreements. The Government of Odisha, Finance Department, had issued revised guidelines on December 10, 2018, superseding previous guidelines from December 7, 2017, to address difficulties faced by contractors regarding works contracts under GST. These revised guidelines provided a procedure for determining the GST-inclusive work value for balance work executed after July 1, 2017, where tenders were invited before that date.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts executed partly or wholly after July 1, 2017, when tenders were invited prior to this date. Petitioner's Contention: The petitioner argued that they are required to pay GST on works contracts, an expense not contemplated at the time of entering into the agreements based on the pre-GST regime. They sought reimbursement for this additional tax burden. Revenue/State's Contention: The revenue/State, through the Additional Government Advocate, presented revised guidelines issued by the Finance Department on December 10, 2018. These guidelines provided a mechanism for calculating the GST-inclusive work value for balance work and stipulated reimbursement or recovery based on the comparison between the revised value and the original agreement value. The State relied on these revised guidelines to address the issue.

Sections Cited

Not explicitly mentioned in the judgment text provided.

AI-generated summary — verify with the full judgment below

02.

24.09.2019

None appears for the parties.

2.

By way of this writ petition, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. 3. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

4.

The Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. Learned Addl. Government Advocate has filed Additional Counter Affidavit of O.P.-authority in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN-CTI-

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.