M/S.M.S.Infraengineers PVT.LTD. vs. State Of Odisha

WP(C)/15217/2019HC OrissaGSTCNR ODHC01046192201925 September 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court noted that the State Government had issued revised guidelines on December 10, 2018, to address the difficulties faced by contractors due to the GST regime for works contracts. These guidelines provide a mechanism to determine the GST-inclusive work value for the balance work executed after July 1, 2017, based on revised rates and tender premiums/discounts. Crucially, the guidelines stipulate that if the revised GST-inclusive work value for the balance work is more than the original agreement work value for that balance work, the works contractor is to be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority was directed to consider and dispose of the representation in light of the revised guidelines dated December 10, 2018, expeditiously, preferably by November 30, 2019. The Court also stated that if the petitioner is aggrieved by the authority's decision, they are at liberty to challenge it, and no coercive action would be taken against the petitioner until November 30, 2019. The issue of reimbursement was thus to be decided by the authority as per the revised guidelines.

Facts

The petitioner, a contractor, filed a writ petition challenging the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that the GST liability was not anticipated when the agreement was entered into. The State, through the Additional Government Advocate, filed an affidavit annexing revised guidelines issued by the Government of Odisha, Finance Department, on December 10, 2018, which superseded earlier guidelines dated December 7, 2017. These revised guidelines addressed the issue of works contracts under GST for tenders invited before July 1, 2017, but executed partly or wholly after that date.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed thereafter? Petitioner's contention: The petitioner argued that they are required to pay GST, a tax not envisaged at the time of entering into the agreement, and therefore, are entitled to reimbursement of this differential tax amount. Revenue's contention: The State submitted revised guidelines issued by the Finance Department on December 10, 2018, which provide a procedure for determining the GST-inclusive work value for balance work executed after July 1, 2017, and stipulate reimbursement if the revised value exceeds the original agreement value. The State relied on these revised guidelines to address the petitioner's grievance.

AI-generated summary — verify with the full judgment below

03.

25.09.2019

None appears for the parties.

2.

By way of this writ petition, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. 3. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

4.

The Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. Learned Addl. Government Advocate has filed Additional Counter Affidavit of O.P.-authority in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN-CTI-TAX-

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.